BiH Water and Sanitation Services Modernization Project

P168943 · Bosnia and Herzegovina · Europe and Central Asia · Financing: T, F, B, 8, 6

Water & SanitationGovernance & Public AdministrationConstruction & Civil WorksTransport & LogisticsMonitoring, Evaluation & LearningGeneral Supplies & Services
48 tenders in the planPlan updated 2026-10-1219 notices on BidsFactory · 0 open · 13 awardedProject page at the World Bank

Procurement plan: every tender of the project

  • Čitluk Municipality Water Supply System — Divided into Two Lots Lot 1: Construction of Jelina Glavica Water Reservoir, capacity V = 2 × 2,000 m³ Lot 2: Construction of pressure pipeline from Biletić Polje Pumping Station to Jelina Glavica Water Reservoir

    PlannedWorksRFB
  • Procurement of measurement and detection equipment

    PlannedGoodsRFQ
  • Benchmarking equipment

    PlannedGoodsRFB
  • Supervision consulting services for the “Construction of a Pressure Pipeline and a New Water Tank of the Water Supply System of the Municipality of Čitluk”

    PlannedConsultingCQS
  • Procurement of maintenance and measuring equipment for the water supply system

    PlannedGoodsRFQ
  • Distribution line in Grad Sunca-Taleža, Trebinje

    PlannedWorksRFB
  • Procurement of measuring equipment

    PlannedGoodsRFQ
  • Procurement of monitoring equipment

    PlannedGoodsRFQ
  • Procurement of vehicle and equipment for unblocking sewage logger

    PlannedGoodsRFB
  • Supervision services for project measures in the City Trebinje

    PlannedConsultingCQS
  • Improvement of None – Revenue Water Management in Water Utility of Republika Srpska

    AdvertisedNon-consulting servicesRFB

    View notice

    Advertised 2026-05-29

    Estimate (Premium)
  • Strengthening organizational, operational and financial capacities of public utility / water supply companies and local self-government units

    AdvertisedConsultingQCBS

    View notice

    Advertised 2026-03-27

    Estimate (Premium)
  • Component 1. Improving the institutional capacity for sector modernization-Optimal and efficient organizational structure and job systematization

    AdvertisedConsultingCQS

    View notice

    Advertised 2026-03-27

    Estimate (Premium)
  • Construction and reconstruction of the sewage collectors in Trn

    AdvertisedWorksRFB

    View noticeWinner: HIDRO-KOP D.O.O BANJALUKA· Awarded 2026-07-13Contract amount (Premium)

    Advertised 2026-03-16

    Estimate (Premium)
  • Rehabilitation and extension of an existing Drinking Water Treatment Plant (DW TP) Tilava

    AdvertisedWorksRFP

    View noticeWinner: MILANOVI TRETMAN VODA KRAGUJEVAC SRBIJA· Awarded 2026-09-03Contract amount (Premium)

    Advertised 2025-11-27

    Estimate (Premium)
  • Procurement of monitoring and other measuring equipment

    ClosedGoodsRFQ

    View noticeWinner: INTERKONT KOMERC D.O.O. LAKTAI· Awarded 2026-09-02Contract amount (Premium)

    Advertised 2026-07-20

    Estimate (Premium)
  • Procurement of monitoring and other measuring equipment

    ClosedGoodsRFQ

    View noticeWinner: INTERKONT KOMERC D.O.O. LAKTAI· Awarded 2026-07-22Contract amount (Premium)

    Advertised 2026-06-05

    Estimate (Premium)
  • Procurement of a Backhoe Loader

    ClosedGoodsRFQ

    View noticeWinner: TERRA BIH D.O.O. SARAJEVO· Awarded 2026-07-06Contract amount (Premium)

    Advertised 2026-05-29

    Estimate (Premium)
  • Procurement of monitoring and other measuring equipment

    ClosedGoodsRFQ

    View noticeWinner: "HIDRANET" DOO· Awarded 2026-04-20Contract amount (Premium)

    Advertised 2026-03-17

    Estimate (Premium)
  • Procurement of factory-new combined backhoe loader

    ClosedGoodsRFQ

    View noticeWinner: TERRA BIH D.O.O.· Awarded 2026-04-15Contract amount (Premium)

    Advertised 2026-03-17

    Estimate (Premium)
  • Individual consultant for providing Terms of Reference preparation services for the procurement of remote reading water meters and other equipment for Water Utilities in the Federation of BiH

    Closedpipeline.cat.individualDirect selection

    View noticeWinner: SEAD BADNJEVIĆ· Awarded 2026-04-07

    Advertised 2026-03-12

    Estimate (Premium)
  • Finance consultant -technical support

    Closedpipeline.cat.individualDirect selection

    View noticeWinner: AZRA BUKVA· Awarded 2026-02-10

    Advertised 2026-02-11

    Estimate (Premium)
  • Procurement specialist

    Closedpipeline.cat.individualDirect selection

    View noticeWinner: ERMINA MULAHUSIC· Awarded 2026-01-30

    Advertised 2026-02-01

    Estimate (Premium)
  • Monitoring and Evaluation officer

    Closedpipeline.cat.individualDirect selection

    View noticeWinner: FAHRO BELKO· Awarded 2026-01-30

    Advertised 2026-01-30

    Estimate (Premium)
  • Procurement of monitoring and other measuring equipmement

    ClosedGoodsRFQ

    View noticeWinner: VMS GROUP D.O.O. SARAJEVO· Awarded 2026-03-30Contract amount (Premium)

    Advertised 2026-01-28

    Estimate (Premium)
  • Financial Management Specialist

    Closedpipeline.cat.individual

    View notice

    Advertised 2025-12-29

    Estimate (Premium)
  • Environmental and social risk management specialist

    Closedpipeline.cat.individual

    View notice

    Advertised 2025-12-29

    Estimate (Premium)
  • Individual Consultant to support Agriculture Project Coordination Unit and the Ministry of Agriculture, Forestry and Water Management of the Republic of Srpska in Technical Assistance for Component 3

    Closedpipeline.cat.individualDirect selection

    Advertised 2025-11-14

    Estimate (Premium)
  • Prtocurement of IT & communication equipment - laptops

    ClosedGoodsRFQ

    Advertised 2025-10-29

    Estimate (Premium)
  • Construction of water supply system Zvornik-West

    ClosedWorksRFB

    Advertised 2025-06-16

    Estimate (Premium)
  • Construction of sewer system for settlement Police

    ClosedWorksRFB

    Advertised 2025-05-20

    Estimate (Premium)
  • Improving management and capacity of (i) the water services sector at the level of local self-governments and (ii) LSG’s water utilities

    ClosedConsultingQCBS

    View noticeWinner: ECONOMIC INSTITUTE D.O.O BANJA LUKA· Awarded 2026-04-24

    Advertised 2025-05-08

    Estimate (Premium)
  • Field Activities Coordinator

    Closedpipeline.cat.individual

    Advertised 2025-04-23

    Estimate (Premium)
  • Rehabilitation of water and wastewater networks in Hilandarska Street Novaka and Pivaševića Street in Prnjavor

    ClosedWorksRFB

    Advertised 2024-12-13

    Estimate (Premium)
  • Connection of water supply systems for Laktaši to Sla tina and Trn

    ClosedWorksRFB

    Advertised 2024-12-13

    Estimate (Premium)
  • Consultant for training delivery and technical support to the APCU/PITs with use of Systematic Tracking of Exchanges in Procurement (STEP) and Contract Management Module (CCM)

    Closedpipeline.cat.individualDirect selection

    Advertised 2024-11-18

    Estimate (Premium)
  • Environmental Specialist (external associate)

    Closedpipeline.cat.individualDirect selection

    Advertised 2024-11-04

    Estimate (Premium)
  • Procurement of vehicles

    ClosedGoodsRFQ

    Advertised 2024-10-10

    Estimate (Premium)
  • Accounting Software

    ClosedGoodsDirect selection

    Advertised 2024-07-18

    Estimate (Premium)
  • IT & Communication Equipment

    ClosedGoodsRFQ

    Advertised 2024-07-09

    Estimate (Premium)
  • Office Furniture

    ClosedGoodsRFQ

    Advertised 2024-07-09

    Estimate (Premium)
  • PIU Staff-Technical Support-Engineer

    Closedpipeline.cat.individualDirect selection

    Advertised 2024-06-01

    Estimate (Premium)
  • PIU Staff-Procurement Specialist

    Closedpipeline.cat.individualDirect selection

    Advertised 2024-06-01

    Estimate (Premium)
  • PIU Staff-Administrative Assistant

    Closedpipeline.cat.individualDirect selection

    Advertised 2024-06-01

    Estimate (Premium)
  • PIU Staff - Financial Specialist

    Closedpipeline.cat.individualDirect selection

    Advertised 2024-06-01

    Estimate (Premium)
  • PIU Staff - Project Manager/APCU Deputy Director

    Closedpipeline.cat.individualDirect selection

    Advertised 2024-06-01

    Estimate (Premium)
  • Technical Assistance for Component 1 & 2

    Closedpipeline.cat.individual

    Advertised 2024-05-21

    Estimate (Premium)
  • Technical Assistance for Component 3

    ClosedConsultingCQS