Integrated Solid Waste Management Project-Phase I
P500392 · Palestine · Middle East, North Africa, Afghanistan, and Pakistan · Financing: T, F, C, 6, 8
Procurement plan: every tender of the project
Design and Supervision for the Construction of Transfer Station
PlannedConsultingQCBSDevelopment of Waste Management Information System (WMIS)
PlannedConsultingQCBSConstruction Supervision of Priority Works at Al-Minya and Zahrat Al-Finjan Sanitary Landfills
PlannedConsultingQCBSPriority Construction Works for Cell 7 at Al-Minya Sanitary Landfill
PlannedWorksRFBConstruction of a Transitional Disposal Cell at ZAF
PlannedWorksRFBSupervision for the Rehabilitation of existing cells, Construction of new cells, and Installation of gas collection and leachate collection/treatment systems at Al-Minya & Zahrat Al-Fenjan Landfills.
PlannedConsultingQCBSUpdate & Development of Legal Framework of the SWM Sector addressing
Plannedpipeline.cat.individualExpansion & Rehabilitation of Zahrat Al-Finjan & Al-Minya Landfills
PlannedWorksRFBEnvironmental & Social Impact Assessment (ESIA) for the selected Transfer Station Location
PlannedConsultingCQSConstruction of Transfer Station in West Bank
PlannedWorksRFBIndependent Verification Agent (for item 2.2.1 above)
PlannedConsultingQCBSDevelopment of standardized financial management for Solid Waste Management Sector
PlannedConsultingQCBSDetailed Study on Optimizing Solid Waste Collection across the West Bank
AdvertisedConsultingQCBSAdvertised 2026-06-15
Estimate (Premium)Hiring an Environmental Expert for the Solid Waste Project - Al-Minya Landfill
Closedpipeline.cat.individualAdvertised 2026-07-30
Estimate (Premium)Environmental and Social Assessment for the Rehabilitation, Upgrade and Expansion of Zahrat Al-Finjan and Al-Minya Sanitary Landfills
ClosedConsultingQCBSView noticeWinner: UNIVERSAL GROUP FOR ENGINEERING AND CONSULTING (UG)· Awarded 2026-09-01
Advertised 2026-03-26
Estimate (Premium)Hiring OHS Specialist for the follow up of the works in Al-Menya Landfill & Dura Transfer Station
Closedpipeline.cat.individualAdvertised 2026-01-07
Estimate (Premium)Hiring OHS Specialist for the follow up of the works in Zahrat Al-Finjan Landfill
Closedpipeline.cat.individualAdvertised 2025-12-29
Estimate (Premium)Supply of Landfill & Transfer Station Equipment
ClosedGoodsRFBAdvertised 2025-12-10
Estimate (Premium)Hiring an Environmental Expert for the Solid Waste Project - Al-Minya Landfill
Closedpipeline.cat.individualAdvertised 2025-11-27
Estimate (Premium)Hiring a Social Expert for the Solid Waste Project - Al-Minya Landfill
Closedpipeline.cat.individualAdvertised 2025-11-24
Estimate (Premium)Hiring a Social Expert for the Solid Waste Project - Zahrat Al-Finjan Landfill
Closedpipeline.cat.individualAdvertised 2025-11-23
Estimate (Premium)Hiring an Environmental Expert for the Solid Waste Project - Zahrat Al-Finjan Landfill
Closedpipeline.cat.individualAdvertised 2025-11-11
Estimate (Premium)Supply and Install Medical Waste Treatment Equipment in Al-Menya Landfill
ClosedGoodsRFBView noticeWinner: GLOBAL ENVIRONMENTAL SERVICES (GES)· Awarded 2026-02-25Contract amount (Premium)
Advertised 2025-11-05
Estimate (Premium)Development of National Hazardous Waste Management Plan
ClosedConsultingQCBSView noticeWinner: KHATIB AND ALAMI CONSOLIDATED ENGINEERING COMPANY· Awarded 2026-04-06
Advertised 2025-10-30
Estimate (Premium)Supply of Bins for solid waste collection for urgent needs
ClosedGoodsRFBView noticeWinner: AL MADANI COMPANY FOR TRADE· Awarded 2026-01-27Contract amount (Premium)
Advertised 2025-10-29
Estimate (Premium)Optimizing Capacity at Zahrat Al-Finjan Sanitary Landfill
Closedpipeline.cat.individualDirect selectionAdvertised 2025-10-01
Estimate (Premium)Establishing baseline for Project Evaluation and Impact Assessment
ClosedConsultingQCBSView noticeWinner: PILLARS CONSULTING· Awarded 2026-01-04
Advertised 2025-08-28
Estimate (Premium)Hiring a Solid Waste Equipment Expert
Closedpipeline.cat.individualDirect selectionAdvertised 2025-06-04
Estimate (Premium)Supply of Bins for post optimizing study - Stage II
ClosedGoodsRFBDetailed Design for the Rehabilitation of existing cells, Construction of new cells, and Installation of gas collection and leachate collection/treatment systems at (1) Zahrat Al-Finjan and (2) Al-Minya Landf
ClosedConsultingQCBSView noticeWinner: GLORY FOR ENGINEERING· Awarded 2026-04-30
Development of Environmental & Social Management Plan (EMSP) for Al Minya and Zahrat Al Fenjan
ClosedConsultingQCBS