The Gambia Infrastructure Project
P504762 · Gambia · Western and Central Africa · Financing: I, D, A, E, 4
Procurement plan: every tender of the project
Recruitment of an Environmental & Social Assistant for the GIP Project
Plannedpipeline.cat.individualConstruction/modernization of customer service centers
PlannedWorksRFBDevelopment of Road Asset Management Software for National Road Authority (NRA)
PlannedNon-consulting servicesRFQProcurement of Road Asset Management Equipment for the National Road Authority
PlannedGoodsRFBUpgrade and construct two primary substations (33KV/11KV) and associated transmission line reconfigurations to boost urban grid reliability and efficiency, replacement of 10 overloaded substations in the GBA
PlannedWorksRFBConsultancy for the development of the road maintenance manual
PlannedConsultingCQSConsultancy for the road Asset Management and low cost data collection technology
PlannedConsultingRFBConsultant to develop fleet renewal scheme
PlannedConsultingCQSConsultancy for the updating of the Gambia national Transport Policy including gender, universal access and Active Mobility
Plannedpipeline.cat.individualTA for the Development of energy Efficiency Labe ls and Standards
PlannedConsultingCQSUpdating Technical Specifications for climate resilient road design for earth, Gravel and Paved Roads including nature based solutions
PlannedConsultingCQSLegislative Review and Regulatory Gap Analysis on the amendments and new Regulations to modernize the Road Traffic Act for a more sustainable road transport
PlannedConsultingCQSConstruction of approx 142 Km of MV lines, 350Km of LV lines, 92 MV/LV substations, provision of prepayment meters for rural beneficiaries
PlannedWorksRFBConsultancy to develop the road map for Vehicle Inspection Centers
PlannedConsultingCQSRecruitment of road safety audit for 150KM of roads nation wide
Plannedpipeline.cat.individualRecruitment of an Environmental Specialist for NAWEC under the Gambia Infrastructure Project (P504762)
Plannedpipeline.cat.individualRecruitment of one Social Specialist for NAWEC under the Gambia Infrastructure Project (P504762)
Plannedpipeline.cat.individualSupply and Delivery of one Project Vehicle
PlannedGoodsRFQRecruitment of a Position of a Social Specialist for National Road Authority
Plannedpipeline.cat.individualEnvironmental Specialist
Plannedpipeline.cat.individualMonitoring and Evaluation Officer
Plannedpipeline.cat.individualInformation Technology Officer (IT)
Plannedpipeline.cat.individualDevelopment of ESIA for the construction of 142 Km of MV lines, 350Km of LV lines, 92 MV sub station and two primary substations (33KV/11KV) and associated transmission line reconfigurationsto boost urban grid reliability
PlannedConsultingCQSDevelopment of ESIA for feasibility studies of 500k m and detail design of 150km of road construction nationwide
AdvertisedConsultingCQSAdvertised 2026-08-10
Estimate (Premium)Resettlement Action Plan/ Livelihood Restoration Plan for feasibility studies for500km and detail design of 1 50km of road construction nationwide.
AdvertisedConsultingCQSAdvertised 2026-08-10
Estimate (Premium)Recruitment of a Consultant to Review and Update the National Transport Policy(2018–2027) With Integration of Active Mobility and Gender Equality and Universal Access
AdvertisedConsultingCQSAdvertised 2026-06-19
Estimate (Premium)Preparation of a Quarry map and Quality of materials to be used in construction
AdvertisedConsultingCQSAdvertised 2026-06-15
Estimate (Premium)Development of a Web-based Energy Information and Reporting System (Energy Dashboard)
AdvertisedNon-consulting servicesRFQAdvertised 2026-03-25
Estimate (Premium)Development of Resettlement Action Plan/ Livelihood Restoration Plan for the 1 42 Km of MV lines, 350Km of LV lines, 92 MV sub station and two primary substations (33KV/11KV) and associated transmission line reconfigurations to boost urban grid reliab
AdvertisedConsultingCQSAdvertised 2026-03-23
Estimate (Premium)Consultancy for the Development of Methodology, training, and Multi-year tariff mode
AdvertisedConsultingCQSAdvertised 2026-03-05
Estimate (Premium)Procurement of owner’s Engineer for site supervision of Village Household and GBA Connectivity (for 2 years)
AdvertisedConsultingQCBSAdvertised 2026-02-27
Estimate (Premium)Development of Draft Regulation and Training beneficiaries on monitoring and enforcement of the Anti-Theft Regulations
AdvertisedConsultingCQSAdvertised 2026-02-02
Estimate (Premium)FEASIBILITY STUDIES CONSULTANCY SERVICES FOR THE STUDY, DESIGN, AND CONSTRUCTION OF ROADS NATIONWIDE
AdvertisedConsultingQCBSAdvertised 2025-04-09
Estimate (Premium)Procurement of Personal Protective Equipment for NAWEC staff
ClosedGoodsRFQView noticeWinner: BL ENTERPRISE· Awarded 2026-03-23Contract amount (Premium)
Advertised 2026-02-16
Estimate (Premium)Recruitment of a Communication Officer for the CPCU of MOFEA
Closedpipeline.cat.individualAdvertised 2026-01-08
Estimate (Premium)Recruitment of an Assistant Environment and Social Specialist for the Gambia Infrastructure Project (GIP)
Closedpipeline.cat.individualAdvertised 2025-10-17
Estimate (Premium)Recruitment of Operations Manager for GIP
Closedpipeline.cat.individualAdvertised 2025-10-01
Estimate (Premium)Recruitment of Project Assistant Accountant
Closedpipeline.cat.individualDirect selectionView noticeWinner: HOREJAH GAYE· Awarded 2025-06-26
Advertised 2025-09-11
Estimate (Premium)Recruitment of Procurement Assistant
Closedpipeline.cat.individualDirect selectionView noticeWinner: ROHEYATOU SEY· Awarded 2025-06-26
Advertised 2025-09-11
Estimate (Premium)Recruitment of Financial Management Specialist
Closedpipeline.cat.individualAdvertised 2025-08-04
Estimate (Premium)Recruitment of Procurement Specialist
Closedpipeline.cat.individualAdvertised 2025-05-12
Estimate (Premium)Recruitment of Consultant for the Development of the Infrastructure Project PPSD
Closedpipeline.cat.individualDirect selectionAdvertised 2025-03-11
Estimate (Premium)Legislative Review/Regulatory Gap and analysis for the Road Sector
ClosedConsultingCQSAdvertised 2025-01-16
Estimate (Premium)Consultancy for the development of Environmental and Social Commitment Plan; Environmental and Social Management Framework; Resettlement Policy Framework; Stakeholder Engagement Plan; and Labour Management Pro
ClosedConsultingCQSAdvertised 2024-12-03
Estimate (Premium)Feasibility Study for 500 km of Priority Road Works and Detailed Design and Bidding Documents for 150km High Priority
ClosedConsultingQCBSAdvertised 2024-11-06
Estimate (Premium)Procurement of motor vehicles for the implementation of GIP Project at the CP CU level.
ClosedGoodsDirect selectionTechnical Assistance Study on detailed cost of energy services
ClosedConsultingCQSConsultant to review, modify and supervise the construction/modernization of customer service centers.
ClosedConsultingCQSView noticeWinner: BENCHMARK CONSTRUCTION AND SURVEYING ENGINEERING· Awarded 2026-06-15
Recruitment of Supervision engineer and road safety audit for 150KM
ClosedConsultingCQSRecruitment of Technical Coordinator
Closedpipeline.cat.individual