Phase 3 Advancing Sustainability in Performance, Infrastructure, and Reliability of the Energy Sector in the West Bank and Gaza
P507260 · Palestine · Middle East, North Africa, Afghanistan, and Pakistan · Financing: T, F, C, 7, 6
Procurement plan: every tender of the project
Enhancing Business Continuity Infrastructure for the Electricity Sector in Palestine for utilities
PlannedConsultingQCBSConstruction of the Green Corridor transmission line segment between the Tubas and the Nablus regions
PlannedGoodsRFBExpansion of Qalandia Substation
PlannedGoodsRFBSupply & Installation of Energy Efficiency Technology for three health facilities (Dura hospital, Thabit Thabit hospital and Al-Berih health directorate)
PlannedGoodsRFBImplementation of MV Network in Ramallah Governorate Abu Michael - Deir Qedies - Jammallah Lines for absorbing PV Solar Plants
PlannedGoodsRFBLUBAN AL-SHARQIAH Medium-Voltage Network Reinforcement Project: Underground Cabling and Substations Installation
PlannedGoodsRFBSupply & Installation of Energy Efficiency Technology for three health facilities and Jericho Hall
PlannedGoodsRFBImplementation of Umm Al-Tut MV ring System in Tubas District Electricity Co (TDECO)
PlannedGoodsRFBSupply and installation of a pilot large-scale centralized battery (storage of PV systems) at one DISCO and one municipality
PlannedGoodsRFBSupply & Installation of Energy Efficiency Technology for pump stations in Jenin area -West Bank
PlannedGoodsRFBSupply of Energy Meters and Combined Measuring Transformer (CMT) for the Rehabilitation of connection points
PlannedGoodsRFBSupply and Installation of Solar Systems to cover Electricity Consumption for Education al Facilities in West Bank.
PlannedGoodsRFBConsultancy Services for the Development and Implementation of the PERC Strategic Information System (SIS)
PlannedConsultingQCBSCompletion of Remaining Works under the Previous Contract – Expansion of Sarra & Tarqumia 161/33 kV Substation
PlannedWorksDirect selectionCompletion of Remaining Works under the Previous Contract – Supply and Installation of Rooftop Solar system in West Bank (Revolving Fund)
PlannedWorksDirect selectionConsultancy Services for the Assessment and Development of an Electric Mobility Transition Framework for Palestine
PlannedConsultingCQSSupply and Installation of rooftop solar systems in West Bank (Revolving Fund) - Phase II
PlannedGoodsRFBConsulting Services for Grid Impact Assessment of Solar PV Plant with Battery Energy Storage System (BESS) Bani N aim, West Bank.
PlannedConsultingCQSSupply and Installation of Solar Systems to cover Electricity consumption for Public Facilities in West Bank.
AdvertisedGoodsRFBAdvertised 2026-07-16
Estimate (Premium)Functional Review of Key Energy Sector Institutions in the West Bank
AdvertisedConsultingCQSAdvertised 2026-04-28
Estimate (Premium)Supply, installation, and configuration of SCADA system (Hardware and Software to develop PETL’s SCADA System)
AdvertisedGoodsRFBAdvertised 2026-04-07
Estimate (Premium)Sector-Wide Cybersecurity, Business Continuity, Framework & Policy Development
AdvertisedConsultingQCBSAdvertised 2026-03-29
Estimate (Premium)Project Execution Consultant for PENRA PMU.
Closedpipeline.cat.individualDirect selectionAdvertised 2026-09-10
Estimate (Premium)Biodiversity Conservation and Sustainable Management of Living Natural Resources Assessment and Management
Closedpipeline.cat.individualAdvertised 2025-11-11
Estimate (Premium)Supply of Electrical Materials for the Rehabilitation of connection points
ClosedGoodsRFBView noticeWinner: SARTABA TRADE & CONTRACTING CO. (SATCO)· Awarded 2026-07-20Contract amount (Premium)
Advertised 2025-11-10
Estimate (Premium)Building New MV Line from AL-FAWWAR Connection Point to YATTA City
ClosedGoodsRFBView noticeWinner: SARTABA TRADE & CONTRACTING CO. (SATCO)· Awarded 2026-02-04Contract amount (Premium)
Supply and Installation of Double Circuit Overhead Lines (OHL) and Underground Cable s (UGCs) from Jalameh Substation to Jenin City to Ensure Reliable Power Supply
ClosedGoodsRFBView noticeWinner: NASERCO FOR CONTRACTING (NASERCO)· Awarded 2026-03-02Contract amount (Premium)
Technical & Financial Audit of ASPIRE Project
ClosedConsultingQCBSView noticeWinner: MAZARS CHARTERED ACCOUNTANTS AND CONSULTANTS· Awarded 2026-04-19
Consulting Services for Hosting Capacity and Grid Impact Assessment of PV and BESS Integration at PETL Substations
ClosedConsultingCQSView noticeWinner: MERCADOS-ARIES INTERNATIONAL (MAI)· Awarded 2026-04-28
Third Party for FAT tests for Yatta-Al Fawwar project
Closedpipeline.cat.individualDirect selectionFactory acceptance Test for the contract of "Supply and Installation of Double Circuit Overhead Lines (OHL) and Underground Cables (UGCs) from Jalameh Substation to Jenin City to Ensure Reliable Power Supply, RFB Reference No.: GZ-PENRA-520368-GO-RFB"
Closedpipeline.cat.individualDirect selectionSupply and Installation of Solar Systems to cover Electricity consumption for Education al Facilities in West Bank.
ClosedGoodsRFB