[Bid Announcement] Sanriku Reconstruction National Park Jodogahama Road (Pedestrian Path) Tunnel Repair Design Outsourcing
Article 1 Scope of Application This special specification applies to the "Sanriku Reconstruction National Park Jodogahama Road (Pedestrian Path) Tunnel Repair Design Outsourcing" business.
Matters not described in these special specifications shall be in accordance with the "Standard Specifications for Design and Other Services (Applicable from October 1, Reiwa 7, Iwate Prefectural Government Land Development Department)".
Article 2 Purpose of Work The purpose of this work is to carry out maintenance and repair design for two pedestrian tunnels and one rock shed on the Michinoku Shiokaze Trail within Sanriku Reconstruction National Park, which are in a state of severe deterioration, to ensure safe passage for pedestrians.
Article 3 Specifications of Facilities to be Repaired and Designed
Facility Name Tunnel A Tunnel B Rock Shed
Location Hitachi-hama Town, Miyako City Hitachi-hama Town, Miyako City Hitachi-hama Town, Miyako City
Tunnel Length 125.5m 30.0m 9.0m
Width 2.0m 2.0m 2.0m
Completion Year Showa 47 Showa 47 Showa 59
Article 4 Scope of Work The scope of work for this project shall be in accordance with the "Standard Specifications for Design and Other Services (Applicable from October 1, Reiwa 7, Iwate Prefectural Government Land Development Department)" Article 6704, Paragraph 2, in addition to the following.
(1) Planning Preparation 1 Work/Planning Preparation/Data Collection and Organization/Field Survey/Consultation with Related Organizations
(2) Tunnel Repair Design 1 set (Rock Shed Steel Material Repair)
- Investigation of cause of deterioration
- Consideration of repair policy
- Design drawings
- Quantity calculation
- Review
- Report creation
(3) Steel Bridge Painting Design 1 set (Rust Prevention (Rock Shed))
- Steel bridge painting design 1
(4) Tunnel Repair Design 1 set (Tunnel Interior Mortar)
- Investigation of cause of deterioration
- Consideration of repair policy
- Design drawings
- Quantity calculation
- Review
- Report creation
(5) Tunnel Entrance Repair Design 1 set (Tunnel Entrance Crack)
- Selection of countermeasures
- Design drawings
- Quantity calculation
- Review
- Report creation
Article 5 Meetings and Consultations Meetings and consultations shall be held a total of four times: at the start of the project, two intermediate meetings, and upon delivery of the final product, and as needed thereafter.
Article 6 Deliverables This work's deliverables shall be subject to electronic delivery, prepared in accordance with the Iwate Prefecture Electronic Delivery Guidelines and national guidelines, and submitted in two copies on electronic media (CD-R, etc.).
In addition to electronic delivery, one copy of the paper deliverable shall be submitted.
Article 7 Loaned Materials The client shall loan materials necessary for the execution of this work.
Article 8 Requirements for Management Engineer and Review Engineer
The requirements for the management engineer and review engineer shall be one of the following qualifications:
① Professional Engineer - Integrated Engineering Management (Civil Engineering - Tunnels)
② Professional Engineer - Civil Engineering (Tunnels)
③ RCCM (Tunnels) with experience as a management engineer in tunnel repair design or tunnel detailed design work
④ Those with over 20 years of experience in tunnel work after graduating from university or a college of technology, and with experience as a management engineer in tunnel repair design or tunnel detailed design work
⑤ Those with over 25 years of experience in tunnel work after graduating from high school or a vocational school, and with experience as a management engineer in tunnel repair design or tunnel detailed design work
Note: The management engineer and review engineer cannot be the same person.
Article 9 Entry into Land during Field Survey
When carrying out this work, please note the following regarding entry into land for surveys:
- Comply with regulations of various laws and ordinances, and consult with the survey official in advance if entry into areas other than public roads is necessary.
- Take utmost care not to alter the terrain or cut down standing trees without permission in the survey area.
Article 10 Doubts
If any doubts arise during this work, the contractor shall consult with the survey official.
Electronic Delivery Special Specifications [Work]
1. Application This work is subject to electronic delivery.
Electronic delivery means "delivery of the final results of each work stage, such as surveys, design, and construction, as electronic deliverables."
Electronic deliverables refer to electronic data created in accordance with the "Iwate Prefecture Electronic Delivery Guidelines" (hereinafter referred to as "Iwate Prefecture Guidelines") and the "Electronic Delivery Guidelines and Standards" (hereinafter referred to as "National Guidelines") established by the country.
2. Electronic Delivery Implementation Classification
The classification of electronic delivery implementation for this work is as follows.
(○) This work will be implemented with electronic delivery as "mandatory."
( ) This work will be decided by "consultation" between the client and the contractor.
* Mark "○" in one of the options.
3. Documents Subject to Electronic Delivery
The classification of documents subject to electronic delivery in this work is as follows.
Folder Document Name Creator Remarks
Client Contractor
REPORT Report ○
DRAWING Drawings ○
PHOTO Photos ○
SURVEY Survey ○
* "○" in the creator column indicates mandatory.
* Documents other than those listed above will be decided through consultation between the client and the contractor.
* In addition to those defined in the Iwate Prefecture Guidelines, list any documents requiring electronic delivery in the table above.
4. Electronic deliverables shall be created in accordance with the Iwate Prefecture Guidelines and National Guidelines, and two copies shall be submitted on electronic media (CD-R).
5. When submitting electronic deliverables, check the deliverables using the Electronic Delivery Check System, SXF browser, etc., confirm that there are no errors, and ensure that virus checks have been performed before submission.
6. When submitting electronic deliverables, create a "Delivery Form for Electronic Media" and submit it along with the electronic media.
Delivery Form for Electronic Media [Work]
Year Month Day
Contractor Address Name
Management Engineer Name Seal
We hereby deliver the electronic media as follows.
Business Name TECRIS Registration Number
Type of Electronic Media Specification Unit Quantity Delivery Date Remarks
CD-R ISO9660 (Level 1) Unit Reiwa Year Month
[Remarks]
○ Check by Electronic Delivery Check System
- Electronic Check System Version: _._._
- Check Date: Reiwa __ Year __ Month __ Day
○ Contents of multiple CD-Rs
- 1/○:
- 2/○: