[Construction Works] Kachu No. 0805 / Announcement of General Competitive Bidding for the Prefectural Upland Area Comprehensive Development Project, Green and Clear Stream Village Shichiso Area Misaka Waterway No. 1 and Other Works
Form No. 2 Individual Bidding Announcement Details [Post-qualification type] Gifu Prefectural Kamo Regional Development Office Manager Tatsuhiko Goto
1. Works subject to general competitive bidding
(1) Kachu No. 0805
Work Name: Work Name
(2) Location: Kamo District, Shichiso Town, Kaminobu area, etc.
(3) Details: Misaka Waterway (Waterway works, ancillary works) L=473.3m, Nakaya Ishibuchi Waterway (Waterway works, ancillary works) L=62.1m, Naka Drainage Channel (Waterway works, ancillary works) L=37.3m, Isshiki Waterway (Waterway works, ancillary works) L=33.0m
(4) Period: Until March 24, Reiwa 9 (2027)
(5) Amount: 36,988,600 Yen (including consumption tax and local consumption tax)
(6) Yes
(7) No
(8) to (17) This work involves scattered construction sites. Therefore, for common temporary facilities costs and site management costs, a "calculation method for scattered construction sites" will be used, calculating common temporary facilities costs and site management costs for each "Green and Clear Stream Village Shichiso Area (Misaka Waterway), Green and Clear Stream Village Shichiso Area (Nakaya Ishibuchi Waterway), Green and Clear Stream Village Shichiso Area (Naka Drainage Channel), Green and Clear Stream Village Shichiso Area (Isshiki Waterway), (hereinafter referred to as the target areas)" due to potential discrepancies between standard calculations and actual construction conditions.
This work is a full two-day weekend (Saturday/Sunday) construction (site closure) based on the principle of full weekly two-day rest.
For details, please refer to the "Implementation Guidelines for Full Weekly Two-Day Weekend (Saturday/Sunday) Construction Ordered by Gifu Prefecture."
This work is a model construction utilizing the Construction Career Up System.
For details, please refer to the "Implementation Guidelines for Model Construction Utilizing the Construction Career Up System Ordered by Gifu Prefecture."
This work is a trial construction of the comprehensive evaluation bidding system for human resource development, aimed at supporting the securing and training of human resources in the construction industry and improving on-site environments.
This work is a comprehensive evaluation bidding system (regional type) where the successful bidder is determined by comprehensively evaluating factors other than price, along with proposals of technical documentation.
This work is subject to a trial of supplementary site management costs to facilitate heatstroke countermeasures, and supplementary site management costs will be adjusted at the time of design change based on the daily maximum temperature.
This work is a trial construction of the comprehensive evaluation bidding system for rural development, aimed at supporting initiatives that contribute to rural development, such as efforts for epidemic prevention work in the livestock industry.
This work is a "model construction utilizing ICT" at the contractor's request.
For details, please refer to the "Implementation Guidelines for Model Construction Utilizing ICT Ordered by the Gifu Prefectural Agriculture, Forestry and Fisheries Department."
Estimated Price
Low Bid Price Investigation System
Minimum Reserve Price System
This work is subject to the obligation of separate demolition, etc., and recycling of specified construction waste materials, based on the Act on the Recycling of Resources in Construction Work (Act No. 104 of 2000).
This work will be conducted using the electronic bidding system.
However, if it is difficult to use the electronic bidding system, written submission may be permitted with prior approval from the head of the contracting organization.
Construction Location
Construction Outline
Construction Period
Bidding Announcement
Announcement of General Competitive Bidding for the Prefectural Upland Area Comprehensive Development Project, Green and Clear Stream Village Shichiso Area Misaka Waterway No. 1 and Other Works
Regarding the Prefectural Upland Area Comprehensive Development Project, Green and Clear Stream Village Shichiso Area Misaka Waterway No. 1 and Other Works, a post-qualification type general competitive bidding will be held, and in accordance with the provisions of Article 127 of the Gifu Prefectural Accounting Regulations (Showa 32, Gifu Prefectural Ordinance No. 19; hereinafter referred to as "Regulations"), this is hereby announced.
The bidding announcement shall consist of "Form No. 1 Common Bidding Announcement Matters [Post-qualification type]" and this document.
"Form No. 1 Common Bidding Announcement Matters [Post-qualification type]" is posted on the Gifu Prefecture website.
This bid will be executed using the electronic bidding system. However, if you have changed your company name, address, or representative and have not updated your IC card, please participate using paper bids.
If you continue to use your current IC card, your bid may be invalidated or your bidding eligibility may be suspended.
Please contact us if you have any questions.
October 27, Reiwa 8 (2026)
Construction Number
Work Name
Prefectural Upland Area Comprehensive Development Project, Green and Clear Stream Village Shichiso Area Misaka Waterway No. 1 and Other Works (Electronic Bidding Eligible Project)
1 2 Bidding Participation Qualifications
The qualifications required for bidding on this work are as follows:
a, b, c
① Works with a contract amount of less than 10 million yen
②
③ Works with a contract amount of 10 million yen or more and less than 45 million yen, and comprehensive evaluation bidding system
Other conditions: As specified in "1. Bidding Participation Qualifications" of "Form No. 1 Common Bidding Announcement Matters [Post-qualification type]."
Your head office must be located within the jurisdiction of the Kamo Regional Development Office as shown in Appendix 2 of "Form No. 1 Common Bidding Announcement Matters [Post-qualification type]."
Contractor for design work, etc.
The contractors for design work, etc., for this project are as follows:
(Co., Ltd.) Kouei Consultant
Conditions regarding technical staff overlap:
This work allows for the application of Special Senior Staff Type 1, Special Senior Staff Type 2, and Article 26-5 of the Construction Industry Act.
Conditions regarding business location:
However,専任 (full-time assignment) is not required in the following cases:
Works with a contract amount of 10 million yen or more and less than 45 million yen, provided that the average construction performance evaluation score for the relevant work type (Civil Engineering Works) of Gifu Prefecture-ordered works in Reiwa 7 and 6 (or Reiwa 5 and 4 if no orders were received in Reiwa 7 and 6) is 75 points or higher.
Conditions regarding the chief or supervising engineer:
The chief or supervising engineer engaged in this work must meet the following criteria (a and c, or b and c) and be available at the start of the contract period for this work.
However, they must be assigned full-time at the start of the actual construction work (December 28, Reiwa 8).
Furthermore,専任 (full-time assignment) is not required when applying Special Senior Staff Type 1, Special Senior Staff Type 2, or Article 26-5 of the Construction Industry Act.
a. Must be a certified Professional Engineer (Agriculture Department "Agricultural Civil Engineering", "Agricultural and Rural Engineering") or possess equivalent or higher qualifications.
b. Must be a certified Class 1 Civil Engineering Construction Management Engineer, Class 2 Civil Engineering Construction Management Engineer (Civil Engineering), or possess equivalent or higher qualifications.
c. Must have experience as a chief engineer, supervising engineer, assistant supervising engineer, or site manager for civil engineering works (total civil engineering works) with a contract amount of 12 million yen or more, as the prime contractor, for works completed and delivered since Reiwa 23 (2011) up to the application deadline.
However, experience as an additional engineer required due to a contract concluded at a price below the low bid price investigation standard price under the low bid price investigation system is excluded (experience as a chief engineer or supervising engineer includes experience under Special Senior Staff Type 1, Special Senior Staff Type 2 (including specially supervising engineers defined by the Construction Industry Act as amended on October 1, Reiwa 2), and Article 26-5 of the Construction Industry Act).
Furthermore, experience as a chief engineer, supervising engineer, specially supervising engineer, assistant supervising engineer, or site manager as a member of a joint venture is limited to cases where the share of participation is 40% or more).
Must have experience in constructing civil engineering works (total civil engineering works) with a contract amount of 19 million yen or more, as the prime contractor, for works completed and delivered since Reiwa 23 (2011).
Conditions regarding construction experience:
Must have experience in constructing the following works as the prime contractor since Reiwa 23 (2011) up to the application deadline.
(Experience as a member of a joint venture is limited to cases where the share of participation is 40% or more).
However, works ordered by the national government or Gifu Prefecture with an evaluation score of less than 65 points are excluded.
Required Construction Industry Permit:
Specific/General (Civil Engineering Construction)
Registered Type and Total Score in Gifu Prefecture Construction Work Bidding Participant List:
Civil Engineering Construction - Total Score 750 points or more
2 3. Responsible Section
Bidding Section: Gifu Prefectural Kamo Regional Development Office
0574-25-3111
Postal Code 505-8508
2610-1 Furui, Mino Kamo City, Gifu Prefecture
Construction Section: Gifu Prefectural Kamo Regional Development Office
0574-25-3111
3rd Floor, Gifu Prefectural Kamo General Government Building
4. Bidding Schedule
Design Document Viewing: From 9:00 AM on Tuesday to 4:00 PM on Wednesday
Questionnaire Submission: From 9:00 AM on Tuesday to 4:00 PM on Monday (via Electronic Bidding System)
(For paper bidders, submit to the Bidding Section)
Response Viewing: From 9:00 AM on Tuesday to 4:00 PM on Wednesday (via Electronic Bidding System)
Application for Viewing: From 9:00 AM on Tuesday to 4:00 PM on Friday (via Electronic Bidding System)
Bidding: From 9:00 AM on Tuesday to 4:00 PM on Wednesday (via Electronic Bidding System)
Opening of Bids: From 10:00 AM on Thursday (via Electronic Bidding System)
Submission of Written Bids (Free format): To the Bidding Section from 1:00 PM on Thursday to 4:00 PM on Friday (Submit in writing to the Bidding Section)
Publication of Bidding Results: Via Bidding Information Service
(For paper bidders, submission in person is permitted, but submission by mail or electronic transmission is not accepted (period and dates are the same).)
Note) Submission documents are described in "Form No. 1 Common Bidding Announcement Matters [Post-qualification type]."
5. Matters concerning the Comprehensive Evaluation Bidding System
(1) Mechanism of the Comprehensive Evaluation Bidding System:
The successful bidder for this work will be determined by the following method:
① A standard score of 100 points will be awarded if the bidding participation qualifications are met.
② An additional score of up to 17.5 points will be awarded based on achievements shown in the technical documentation.
(2) Evaluation Items:
The following items will be evaluated:
(a) Corporate capabilities
(b) Technical staff capabilities
(c) Regional requirements
Response to complaints:
Within 10 days from the day after the final day for filing a complaint (excluding prefectural holidays), in principle.
Date of Bid Award
③ The method of determining the successful bidder using the value calculated by dividing the sum of the awarded standard score and additional score by the bidder's bid price (hereinafter referred to as the "evaluation value").
The outline is shown below, but specific technical requirements and bidding evaluation criteria are clearly stated in "Details of Comprehensive Evaluation Bidding System."
Submission of Confirmation Documents: Reiwa 8, November 19 (For successful bidder candidates only)
Reiwa 8, November 20
Complaint Filing: Within 7 days from the date of notification of the bid participation notice or bid participation qualification disqualification notice (excluding prefectural holidays).
Submission of Bids, etc.: Reiwa 8, November 17
Reiwa 8, November 18
Reiwa 8, November 19
3rd Floor, Kamo General Government Building, Kamo Regional Development Office
*For paper bidders, bring a copy of the bid participation qualification confirmation notice.
Reiwa 8, November 18
Reiwa 8, October 27
Reiwa 8, November 4
*For paper bidders, submit to the Bidding Section.
Notification of Bid Participation Notice: Reiwa 8, November 6
Reiwa 8, October 27
Reiwa 8, November 18
Also available for viewing at the Bidding Section.
Reiwa 8, October 27
Reiwa 8, November 9
Reiwa 8, October 27
General Affairs Division, Management Coordination Section (Ext. 404)
Agricultural Land Development Division, Rural Development Section (Ext. 418)
Procedure Period/Date Method/Location
Category Responsible Section Phone Number Address
3 1. Mechanism of Comprehensive Evaluation Bidding System
① The mechanism of the comprehensive evaluation bidding system is shown below.
◎A ○B ×C ×D
A: Successful bidder
◎B: Unsuccessful bidder (exceeds standard evaluation value but evaluation value (graph slope) is lower than A)
○C: Unsuccessful bidder (exceeds estimated price)
×D: Unsuccessful bidder (below standard evaluation value)
② Method of determining the successful bidder:
Meet the following conditions:
a. Bid price ≤ Estimated price
b. Meet the minimum requirements (standard proposal conditions).
(Standard score or higher)
c. Evaluation value ≥ Standard evaluation value (If a and b are met, c is automatically met).
2. Evaluation Items and Evaluation Indicators:
① Evaluation Items:
(a) Corporate capabilities
(b) Capabilities of the assigned technical staff
(c) Regional requirements
② Evaluation Indicators:
(a) Evaluated based on construction performance score, experience in similar/analogous works, and human resource development initiatives.
(b) Evaluated based on experience in similar/analogous works.
3. Standard Score and Additional Score:
① Standard Score: 100 points will be awarded as the standard score if the standard proposal conditions are met.
② Additional Score: Points will be awarded according to the evaluation criteria.
4. Awarding of Additional Points:
The criteria for awarding additional points to bidders are shown in the table below.
Evaluation Items and Points by Method
Construction Performance Score ○ 2
Construction Experience ○ 1
Human Resource Development Initiatives ○ 1
Construction Experience ○ 1
Business Location ○ 1
Disaster Agreement Participation, etc. ○ 2
Epidemic Prevention Agreement Participation, etc. ○ 1
Volunteer Activities ○ 1
○ Agricultural Entry ○ 1
Local Area Construction Experience ○ 1
Snow Removal Work Experience, etc. ○ 2
○ 1
○ ○
Total 17.5
Corporate Capabilities
Assigned Technical Staff Capabilities
Regional Requirements
Volunteer Activities (Land Improvement Facilities Related)
0.5
Holiday and Nighttime Road Maintenance Work Experience
Holiday and Nighttime River/Sabo Maintenance Work Experience
0.5
Utilization of Prefectural Companies 1.5
*If there are two or more bidders who meet the bidding conditions, the bidder with the highest evaluation value will be the successful bidder.
Furthermore, if the evaluation values are the same, the successful bidder will be determined by lottery.