[Gunrin No. 0806] Public Announcement of General Competitive Bidding for Forest Environmental Conservation and Development Project Forestry Road Naruto to Rokunori Line (Section 2) Construction
Form No. 2 [Post-evaluation Type] Director of Gifu Prefectural Gujo Agricultural Affairs Office, Yukihiko Yamauchi
1. Construction to be put to general competitive bidding
(1) Construction Number: Gunrin No. 0806
Construction Name: Construction Name Construction Name
(2) Construction Location: Rokunori, Shirotori-cho, Gujo City
Line Adjustment
(3) Scope of Construction: Width 3.0 (3.6)m, Construction Length 203.1m, Completed Length 181.2m
Earthwork: Excavation 2,370m3, Embankment 2,011m3
Slope Work: Vegetation base spraying 660.4m2, Concrete spraying 98.4m2, Vegetation mat work 183.6m2, Seed spraying 906.8m2
Drainage Work: Culvert 8.6m, U-shaped ditch 48.0m
Roadbed Work: Gravel paving 414.1m2
(4) Construction Period: From the contract date to March 24, Reiwa 9
(5) Estimated Price: 31,556,800 yen (including consumption tax and local consumption tax)
(6) Low Bid Price Investigation System: Yes
(7) Minimum Restriction Price System: None
(8) (9) (10) (11) (12) (13) (14) (15) (16) (17) (18) This construction is a full two-day weekend work (site closure) based on the principle of full two-day weekends.
For details, please refer to the "Implementation Guidelines for Full Two-Day Weekend Work (Saturday and Sunday) Commissioned by Gifu Prefecture".
This construction is a trial project for the correction of site management costs contributing to heatstroke countermeasures, and the correction of site management costs will be carried out during the design change based on the daily maximum temperature.
This construction is a model project for improving the construction site environment requested by the contractor.
For details, please refer to the "Implementation Guidelines for Model Projects for Improving Construction Site Environment Commissioned by Gifu Prefecture".
This construction is a project utilizing the ASP-based information sharing system of the contractor-requesting method.
For details, please refer to the "Gifu Prefecture Information Sharing System Operation Guidelines (Construction Edition)".
This construction is a model project utilizing ICT requested by the contractor.
For details, please refer to the "Implementation Guidelines for Trial Use of ICT in Forest Conservation and Development Projects" etc. established by the Forestry Agency.
BID ANNOUNCEMENT (INDIVIDUAL MATTERS)
Public Announcement of General Competitive Bidding for Forest Environmental Conservation and Development Project Forestry Road Naruto to Rokunori Line (Section 2) Construction
This construction is a trial project for the rural development type comprehensive evaluation bidding method, which aims to support initiatives that contribute to rural development, such as measures against livestock infectious diseases in the construction industry.
This construction is a trial project for the human resource development type comprehensive evaluation bidding method, which aims to support the securing and training of human resources and the improvement of the working environment in the construction industry.
This construction is a project for which the "Act on the Promotion of Proper Treatment of Construction Materials, etc." (Heisei 12, Act No. 104) mandates the implementation of separate demolition, etc. and recycling of specified construction material waste.
This construction is a comprehensive evaluation bidding project (regional type) that determines the successful bidder by evaluating elements other than price along with price, based on the submission of technical proposals.
August 12, Reiwa 8
This construction will be carried out using the electronic bidding system.
However, if it is difficult to use the electronic bidding system, written submission may be permitted with prior approval from the head of the contracting authority.
Forest Environmental Conservation and Development Project Forestry Road Naruto to Rokunori Line (Section 2) Construction (Electronic Bidding Target Project)
Public Announcement of General Competitive Bidding for Forest Environmental Conservation and Development Project Forestry Road Naruto to Rokunori Line (Section 2) Construction
We will conduct a post-evaluation type general competitive bidding for the Forest Environmental Conservation and Development Project Forestry Road Naruto to Rokunori Line (Section 2) Construction, and hereby announce it in accordance with the provisions of Article 127 of the Gifu Prefecture Accounting Regulations (Showa 32, Gifu Prefecture Ordinance No. 19, hereinafter referred to as "Regulations").
The bid announcement shall consist of "Form No. 1 Bid Announcement Common Matters [Post-evaluation Type]" and this document.
"Form No. 1 Bid Announcement Common Matters [Post-evaluation Type]" is posted on the Gifu Prefecture website.
This bid will be conducted using the electronic bidding system. However, if you have changed your trade name or name, address, or representative and have not completed the IC card change procedures, please participate using paper bidding.
If you continue to use your IC card, your bid may be invalidated or you may be subject to measures to suspend bidding qualifications.
Please consult us if you have any questions.
This construction is a model project utilizing the construction career up system requested by the contractor.
For details, please refer to the "Implementation Guidelines for Model Projects Utilizing the Construction Career Up System Commissioned by Gifu Prefecture".
2. Bidding Qualifications
The qualifications required for participating in the bidding for this construction are as follows:
Eye U ① ② ③
3. Responsible Department
Bidding Section | 0575-67-1111 | 1727-2 Hachiman-cho Hatsune, Gujo City, Gifu Prefecture, 501-4292
Construction Section | 0575-67-1111 | Gujo General Government Building, 4th Floor (Ext. 253)
Technician Concurrent Service Conditions: This construction allows for the application of Exclusive Special Type 1, Exclusive Special Type 2, and Article 26-5 of the Construction Industry Act.
Specific/General (Civil Engineering Construction) | Registered Industry and Overall Score in Gifu Prefecture Construction Work Bidding Participant Qualification List: Civil Engineering Construction, Overall Score 750 points or more
Construction Experience Conditions: Must have experience as the prime contractor in civil engineering works as defined by the Construction Industry Act, with a completed delivery and a construction cost of 9.5 million yen or more since FY2023 up to the application deadline, serving as a chief technician, supervising technician, supervising technician assistant, or site agent. However, this excludes experience as an additional technician required in cases where the contract is concluded at a price below the low bid price investigation standard price under the low bid price investigation system. (Experience as a chief technician or supervising technician includes experience as an Exclusive Special Type 1, Exclusive Special Type 2 (including special supervising technician defined by the Construction Industry Act revised on October 1, Reiwa 2), and chief technician and supervising technician to which Article 26-5 of the Construction Industry Act applies. Furthermore, experience as a chief technician, supervising technician, supervising technician assistant, or site agent as a member of a joint venture is limited to those with an equity ratio of 40% or more.)
However, exclusivity is not required if any of the following (1) to (3) apply.
Works with a contract price of less than 10 million yen.
Works with a contract price of 10 million yen or more but less than 45 million yen, provided that the average construction performance evaluation score for the relevant work type (*1) of works commissioned by Gifu Prefecture in Reiwa 7 and Reiwa 6 is 75 points or more (if there is no record of receiving works of the relevant work type (*1) commissioned by Gifu Prefecture in Reiwa 7 and Reiwa 6, the average construction performance evaluation score for the relevant work type (*1) of works commissioned by Gifu Prefecture in Reiwa 5 and Reiwa 4 is 75 points or more).
Works with a contract price of 10 million yen or more but less than 45 million yen, which are comprehensive evaluation bidding projects.
*1: Work type classifications defined by the Construction Industry Act, such as "Civil Engineering Works," "Building Works," and "Pavement."
Required Construction Industry Permit | Design Services Contractor, etc.: Must have qualifications as a Class 1 Civil Engineering Construction Management Engineer, Class 2 Civil Engineering Construction Management Engineer, or equivalent or higher.
Must have experience in constructing the following works as the prime contractor since FY2023 up to the application deadline. (Experience as a member of a joint venture is limited to those with an equity ratio of 40% or more.)
However, for works commissioned by the national government or Gifu Prefecture, excluding those with a construction performance evaluation score of less than 65 points.
- Experience in constructing civil engineering works as defined by the Construction Industry Act, with a completed delivery and a construction cost of 16 million yen or more.
Assigned Technician Conditions | However, for works commissioned by the national government or Gifu Prefecture, excluding those with a construction performance evaluation score of less than 65 points.
This construction requires the chief technician or supervising technician engaged in this project to meet the following criteria (a and c, or b and c) and be assignable at the start of the contract period for this construction. However, on the start date of on-site construction for this project (October 9, Reiwa 8), they must be assignable exclusively. Furthermore, exclusivity is not required when applying Exclusive Special Type 1 and Exclusive Special Type 2, or Article 26-5 of the Construction Industry Act.
Engineer (Construction Department, Agriculture Department "Agricultural Civil Engineering", "Agricultural and Rural Engineering", Forestry Department "Forestry Civil Engineering"), or equivalent or higher qualifications.
Specific/General (Civil Engineering Construction) | Registered Industry and Overall Score in Gifu Prefecture Construction Work Bidding Participant Qualification List: Civil Engineering Construction
4. Bidding Schedule
Procedure | Period/Deadline | Method/Location
Design Document Inspection | From 9:00 AM on Wednesday, August 12, Reiwa 8 to 4:00 PM on Wednesday, September 3, Reiwa 8 | Download from electronic bidding system, etc.
Inquiry Reception | From 9:00 AM on Wednesday, August 12, Reiwa 8 to 4:00 PM on Monday, August 17, Reiwa 8 | Via electronic bidding system. * For paper bidders, submit to the bidding department.
Answer Document Viewing | From 9:00 AM on Wednesday, August 12, Reiwa 8 to 4:00 PM on Wednesday, September 3, Reiwa 8 | Via electronic bidding system. Also available for inspection at the bidding department.
Bidding Participation Application | From 9:00 AM on Wednesday, August 12, Reiwa 8 to 4:00 PM on Tuesday, August 18, Reiwa 8 | Via electronic bidding system.
Qualification Confirmation | By Thursday, September 2, Reiwa 8 | Deadline for submission of bids by email
Bid Submission | From 9:00 AM on Wednesday, September 2, Reiwa 8 to 4:00 PM on Thursday, September 3, Reiwa 8 | Method is as per "1. Matters Concerning Bidding (11)"
Bid Opening | From 10:00 AM on Thursday, September 3, Reiwa 8 | Gujo General Government Building, Room 5-South 1 Conference Room
Submission of Qualification Confirmation Documents for Successful Bidder Candidate | By 4:00 PM on Monday, September 7, Reiwa 8 | In-person or mail submission to the bidding department.
Complaint Filing | Within 7 days from the date of notification of the Bid Participation Notice or Bid Qualification Disqualification Notice (excluding prefectural holidays) | Submit to the bidding department in person (free format).
Response to Complaint Filing | Within 10 days from the day after the final day for filing a complaint (excluding prefectural holidays) | Respond in writing.
Bid Result Announcement | On the date of successful bid determination | Via Bidding Information Service or Prefectural Website. Also available for inspection at the bidding department.
* For paper bidders, in-person submission is permitted, but submission by mail or electronic transmission will not be accepted (period and dates are the same).
Note) Submission documents are described in "Form No. 1 Bid Announcement Common Matters [Post-evaluation Type]".
5. Matters Concerning Comprehensive Evaluation Bidding Method:
(1) Mechanism of Comprehensive Evaluation Bidding Method: The successful bidder will be determined by the following method.
① A standard score of 100 points will be awarded if the bidding qualifications are met.
② A maximum of 16 additional points will be awarded based on experience, etc. shown in the technical proposal.
(2) Evaluation Items: The following items will be evaluated.
(a) Matters concerning corporate capabilities
(b) Matters concerning the capabilities of the assigned technician
(c) Matters concerning regional requirements
6. Other:
(1) Regarding the response to complaint filing, within 10 days from the day after the final day for filing a complaint (excluding prefectural holidays), in principle.
On the date of successful bid determination.
③ The successful bidder will be determined by calculating the value obtained by dividing the sum of the standard score and additional points by the bidder's bid price (hereinafter referred to as "evaluation value").