[Gunanaka No. 0810] Prefectural Upland Area Comprehensive Development Project Shiratori Hokubu District Jinja/Shibahara Settlement Road No. 6 Construction General Competitive Bidding Announcement
Form No. 2 [Post-Bid Review Type]
Shinichi Yamauchi, Director of Gifu Prefectural Gujo Agricultural and Forestry Office
1. Construction to be Put to Open Competitive Bidding
(1) Construction Number: Gunanaka No. 0810
(2) Construction Location: Within Nika-machi, Shiratori-cho, Gujo City.
(3) Construction Outline: Road work L=112.7m, W=3.5(4.0)m . Gravity retaining wall (H=1.0-2.15m) L=80.0m. L-shaped ditch L=44.5m. Pavement work A=461.5m2.
(4) Construction Period: From the date of contract to March 26, Reiwa 9 (2027).
(5) Estimated Price: 33,250,800 yen (including consumption tax and local consumption tax).
(6) Yes.
(7) No.
(8) to (18) This project is a model construction utilizing the Construction Career Up System upon request from the contractor. For details, refer to the "Implementation Guidelines for Model Construction Utilizing the Construction Career Up System Ordered by Gifu Prefecture".
BID ANNOUNCEMENT
(Individual Matters)
Prefectural Upland Area Comprehensive Development Project Shiratori Hokubu District Jinja/Shibahara Settlement Road No. 6 Construction General Competitive Bidding Announcement
This project is a trial project using the rural development type comprehensive evaluation winning bid method, which aims to support initiatives contributing to rural development, such as measures against epidemic diseases in livestock in the construction industry.
This project is a trial project using the human resource development type comprehensive evaluation winning bid method, which aims to support securing and developing human resources and improving the working environment in the construction industry.
This project is subject to the obligation of separate demolition, etc., and recycling of specified construction materials, based on the Act on the Recycling of Resources in Construction Materials (2000 Law No. 104).
This project is a comprehensive evaluation winning bid method (regional type) project that determines the successful bidder by comprehensively evaluating factors other than price along with price, based on technical documentation proposals.
October 27, Reiwa 8 (2026)
This project will be conducted using the electronic bidding system. However, those who find it difficult to use the electronic bidding system may submit documents in writing with prior approval from the head of the ordering institution.
Prefectural Upland Area Comprehensive Development Project Shiratori Hokubu District Jinja/Shibahara Settlement Road No. 6 Construction (Electronic Bidding Target Project)
Regarding the Prefectural Upland Area Comprehensive Development Project Shiratori Hokubu District Jinja/Shibahara Settlement Road No. 6 Construction, a post-bid review type general competitive bidding will be conducted, and announced in accordance with the provisions of Article 127 of the Gifu Prefecture Accounting Regulations (1957 Gifu Prefecture Rule No. 19) (hereinafter referred to as "Regulations").
The bid announcement consists of "Form No. 1 Bid Announcement Common Matters [Post-Bid Review Type]" and this document. "Form No. 1 Bid Announcement Common Matters [Post-Bid Review Type]" is posted on the Gifu Prefecture website.
This bid is executed via the electronic bidding system, but if you have not updated your IC card after changing your company name, address, or representative, please participate using paper bidding. If you continue to use your current IC card, your bid may be invalidated or you may be subject to bid participation qualification suspension measures. Please consult us if you have any questions.
Low Bid Price Investigation System / Minimum Reserve Price System
This project is a contractor-requested "Model Construction Utilizing ICT". For details, refer to the "Implementation Guidelines for Model Construction Utilizing ICT Ordered by Gifu Prefecture".
This project is a complete two-day weekend work system (site closure) based on the principle of complete two-day weekends. For details, refer to the "Implementation Guidelines for Complete Two-Day Weekend Work (Saturday and Sunday) Ordered by Gifu Prefecture".
This project is subject to the trial of supplementary site management costs based on the situation of maximum daily temperature, which contributes to heatstroke countermeasures, and the supplementary site management costs will be changed during the design modification.
This project is a model construction for improving the construction site environment upon request from the contractor. For details, refer to the "Implementation Guidelines for Model Construction for Improving Construction Site Environment Ordered by Gifu Prefecture".
This project is a construction utilizing the ASP-based information sharing system of the contractor's preferred type. For details, refer to the "Gifu Prefecture Information Sharing System Operation Guidelines (Construction Version)".
2. Bid Participation Qualifications:
The qualifications required for bidders in this project are as follows.
a. b. c. ① ② ③
3. Department in Charge:
Bid Management Department: 0575-67-1111
〒501-4292 1727-2 Hatsune, Gujo Hachiman-cho, Gujo City, Gifu Prefecture.
Construction Management Department: 0575-67-1111 Gujo General Government Building, 4th Floor (Extension 203).
Gujo Agricultural and Forestry Office, Gifu Prefecture
"Form No. 1 Bid Announcement Common Matters [Post-Bid Review Type]" "Section 1 Matters Related to Bid Participation Qualifications" as shown.
Other Conditions:
Department in Charge: Phone Number: Address: Category:
Required Construction Industry License: Design Services, etc. Contractor, etc.
1st Class Civil Engineering Construction Management Engineer, 2nd Class Civil Engineering Construction Management Engineer, or equivalent qualification holder.
Must have construction performance records for work meeting the following requirements, completed and delivered as the prime contractor since Reiwa 13 (2001) (for members of joint ventures, only those with an investment ratio of 40% or more).
- Construction work of "Civil Engineering Works" as defined by the Building Contractors Act, with a completed contract amount of 17 million yen or more.
Conditions Regarding Assigned Technical Personnel:
Must be able to assign a chief engineer or supervising engineer (civil engineering) who meets the following criteria (a and c, or b and c) and can be assigned at the start of the contract period for this project. However, they must be able to be assigned exclusively on the day the site construction for this project begins (December 25, Reiwa 8 (2026)). However, exclusivity is not required when applying Special Rule No. 1, Special Rule No. 2, and Article 26-5 of the Building Contractors Act.
Construction work with a contract amount of less than 10 million yen.
Even for construction work with a contract amount of 10 million yen or more but less than 45 million yen, if the average construction performance evaluation score for the relevant work type (※1) in Gifu Prefecture ordered projects in Reiwa 7 and Reiwa 6 (2025 and 2024) is 75 points or higher (if there are no orders for the relevant work type (※1) in Gifu Prefecture ordered projects in Reiwa 7 and Reiwa 6, then the average score for Reiwa 5 and Reiwa 4 (2023 and 2022) is 75 points or higher), the contractor must be qualified.
Construction Performance Conditions:
Comprehensive evaluation winning bid projects with a contract amount of 10 million yen or more but less than 45 million yen.
※1: Construction types defined by the Building Contractors Act, such as "Civil Engineering Works", "General Construction Works", and "Pavement".
Agricultural Land Development Division, Rural Development Section
Registered Industries and Comprehensive Scores in the Gifu Prefecture Construction Project Bid Participation Qualification List.
Conditions Regarding Business Office Location:
Union Co., Ltd.
However, exclusivity is not required if any of the following ① to ③ apply.
Must be a certified professional engineer (construction sector, agriculture sector "agricultural civil engineering", "agricultural rural engineering", forestry sector "forest civil engineering") or hold an equivalent or higher qualification.
Must have experience as a chief engineer, supervising engineer, supervising engineer assistant, or site supervisor in at least one project of the same type of service completed and delivered on or after April 1, Reiwa 13 (2001) by the Application Deadline (for members of joint ventures, only those with an investment ratio of 40% or more).
However, excluding work where the construction performance evaluation score was less than 65 points for projects ordered by the national government and Gifu Prefecture.
(This includes experience as a chief engineer or supervising engineer to whom Special Rule No. 1, Special Rule No. 2 (including special supervising engineers defined by the Building Contractors Act revised on October 1, Reiwa 2 (2020)), and Article 26-5 of the Building Contractors Act applied, and experience as a chief engineer, supervising engineer, supervising engineer assistant, or site supervisor as a member of a joint venture, limited to those with an investment ratio of 40% or more).
Conditions for Technical Personnel Concurrent Assignment:
This project allows for the application of Special Rule No. 1, Special Rule No. 2, and Article 26-5 of the Building Contractors Act.
Specific/General (Civil Engineering Works)
Civil Engineering Works - Comprehensive Score 750 points or higher.
4. Bidding Schedule:
Design Document Viewing: (Tuesday) From 9:00 AM to (Wednesday) 4:00 PM. Download from the electronic bidding system, etc.
Question Submission: (Tuesday) From 9:00 AM to (Monday) 4:00 PM. Submit via electronic bidding system. * Paper bidders must bring to the bid management department.
Answer Viewing: (Tuesday) From 9:00 AM to (Thursday) 4:00 PM. Also available for viewing at the ordering institution.
Bid Form Submission: From (Tuesday) 9:00 AM to (Wednesday) 4:00 PM. Submit via electronic bidding system.
Bid Opening: (Thursday) From 10:00 AM. Gujo General Government Building, South 5-1 Conference Room.
Bid Result Publication: Via the Bidding Information Service or the prefectural website. Also available for viewing at the bid management department.
* For paper bidders, submission in person is permitted, but submission by mail or electronic transmission is not accepted. (Period and dates are the same).
Note) Submission documents are described in "Form No. 1 Bid Announcement Common Matters [Post-Bid Review Type]".
5. Matters Related to Comprehensive Evaluation Winning Bid Method:
(1) Mechanism of Comprehensive Evaluation Winning Bid Method:
The successful bidder for this project will be determined by the following method.
① Upon meeting the bid participation qualifications, a standard score of 100 points will be awarded.
② Additional points of up to 17.5 points will be awarded based on achievements, etc., shown in the technical documentation.
(2) Evaluation Items:
The following items will be evaluated.
(a) Matters related to corporate capabilities.
(b) Matters related to the capabilities of the assigned technical personnel.
(c) Matters related to regional requirements.
6.