Construction Work for the Renovation of Agricultural Dam Facilities in the Kushiji Area (Part 4) - Ordering Documents
Work Name: Construction Work for the Renovation of Agricultural Dam Facilities in the Kushiji Area (Part 4)
Location: Within Nago City, Kushiji
Construction Period: From Reiwa 8 (Year) Month Day to Reiwa 9 (Year) March 18
Article 1 (Application of Common Specifications for Facility Machinery Construction, etc.)
When carrying out construction for this work, it must be implemented based on the "Common Specifications for Facility Machinery Construction, etc." established by the Okinawa Prefectural Department of Agriculture, Forestry, and Fisheries.
Article 2 (Special Provisions and Additional Matters to the Common Specifications for Facility Machinery Construction, etc.)
Special provisions and additional matters to the Common Specifications for Facility Machinery Construction, etc. are as follows.
Special Specifications
Nago City
Section
Item
Special Provisions and Additional Specifications
3
Application
1 This special specification applies to.
4
General Matters
1 This work shall be constructed based on these special specifications and drawings. Matters not described in these special specifications shall be constructed in accordance with the Common Specifications for Facility Machinery Construction, etc., the Facility Machinery Construction Work Management Standards (established by the Department of Agriculture, Forestry, and Fisheries), the Standard Specifications for Concrete, the Labor Standards Act, and other relevant laws, regulations, and reference materials.
Construction shall prioritize these special specifications and drawings, followed by the Common Specifications for Facility Machinery Construction, etc., Facility Machinery Construction Work Management Standards, and other reference materials.
2 When there are unclear points or doubts in the design documents during the commencement or execution of the work, the contractor shall promptly consult with the supervisor. Any damages incurred due to failure to report to the supervisor shall be borne entirely by the contractor.
5
1
In accordance with Article 26 of the Construction Industry Act, the chief engineer or supervising engineer to be assigned exclusively to the construction site must have been employed by the contractor (company) for three months or more prior to the bid execution date.
2
Upon submission of the commencement notification, the contractor shall present documents proving the employment relationship of the chief engineer or supervising engineer to be assigned exclusively to the construction site (copy of health insurance insured person's card, etc.).
6
Procedures necessary for the work
1
Regarding procedures necessary for the work, the contractor shall coordinate with relevant parties and public offices at their own responsibility.
7
Interpretation of doubts
1
Prior to the commencement of work, the contractor shall conduct necessary surveys and measurements, confirm the design documents, and if any doubts arise regarding the contents of the specifications and design documents, they shall be resolved through consultation with the supervisor before proceeding with construction.
Furthermore, any damages incurred due to failure to consult shall be borne entirely by the contractor.
Reiwa 8 (Year) Month Day to Reiwa 9 (Year) March 18
Construction Work for the Renovation of Agricultural Dam Facilities in the Kushiji Area (Part 4)
Regarding the employment relationship of the chief engineer and supervising engineer
Special Specifications
Nago City
Section
Item
Special Provisions and Additional Specifications
8
1
The contractor shall set up a site office within or near the construction site. The office shall display the outline of this work, the implementation schedule, organizational chart, weather map, and other necessary information in a way that can be understood at a glance.
9
1
Implementation of safety and training, etc., shall be in accordance with the provisions of the Common Specifications for Civil Engineering Works.
10
1
When formulating the construction plan, sufficient consideration shall be given to the surrounding environment and agricultural management, and the construction methods, machinery, and materials to be used shall be thoroughly examined to avoid infringing upon the living environment of nearby residents.
11
1
During the execution of the work, meticulous consideration shall be given during the preparation of the construction plan to minimize friction and trouble with local residents due to dust, turbid water, noise, vibration, traffic accidents, etc.
12
1
If it is necessary to rent private land for the execution of the work, all actions, unless otherwise instructed, shall be handled at the contractor's responsibility, including negotiations with local parties and compensation.
13
1
During the construction period, unauthorized entry into private land or scattering of materials and equipment, which may cause disputes, must be strictly avoided. When entering areas other than the construction site, the consent of the owner must always be obtained.
14
1
Overloading of construction machinery and equipment shall be prevented, and dump trucks that have been illegally modified shall not be allowed to enter the construction site.
15
1
The machinery and materials to be used in this work shall be described in the construction plan. For materials, their shape, dimensions, material, strength, manufacturer, etc., shall be approved in advance.
16
Priority use of prefectural products
1
Materials and equipment used in this work shall be produced or manufactured within the prefecture. If the quality and price are appropriate, efforts shall be made to prioritize their use.
17
Prevention of illegal excavation of Ryukyu limestone
1
When using Ryukyu limestone (excluding Paleozoic limestone) as construction material, a certificate of origin (original) must be submitted.