Road Relocation Work for Municipal Road Gonoara-Gatashita Line (Section 2).
Ichikikushino City Announcement No. 62, September 10, Reiwa 8.
To Kenji Nakaya, Mayor of Ichikikushino City.
Bidding planned price (excluding tax), whether a minimum reserve price is set, whether a breakdown of construction costs is required.
Grading: Class A.
From to to to Construction Section Tel: 0996-21-5156 Fax: 0996-21-5192 Tel: 0996-33-5629 Fax: 0996-32-3124 to to from.
Regarding the following construction work, a public competitive tender will be held as follows, in accordance with the provisions of Article 2 of the Ichikikushino City Contract Regulations (Ichikikushino City Ordinance No. 49 of Reiwa 17).
NOTICE
NOTICE OF CONSTRUCTION WORK
Ordered Work Type: Waterworks Construction
Work Number: Water Single No. 10
Work Name: Road Relocation Work for Municipal Road Gonoara-Gatashita Line (Section 2)
Work Location: Ichikikushino City, Ebisu Town, etc.
Tendering Method: Conditional Public Competitive Tender (Electronic Bidding)
Work Outline: [Municipal Road Gonoara-Gatashita Line] Construction length L=140.8m, Water distribution pipe laying work HPPEφ200 L=61.5m, HPPEφ100 L=63.1m, Valve installation work φ150x4 units, φ50x1 unit, Fire hydrant installation work φ75x1 unit, Water supply connections x2.
[Municipal Road Beppu-Shimohira Line] Construction length L=64.9m, Water distribution pipe laying work HPPEφ75 L=48.0m, Valve installation work φ75x1 unit, φ50x2 units, φ40x1 unit, Water supply connections x3.
Construction Period: From the date of contract to February 26, Reiwa 9.
Post-disclosure: Yes
Required
Ordering Classification/Conditions:
Must meet the following conditions:
Ichikikushino City Bidding Qualification for Waterworks Construction
Bid Bond: Exempt
Contract Security: If the contract amount exceeds 5 million yen, 10% or more of the contract amount.
Advance Payment: If the contract amount is 1 million yen or more, up to 40% of the contract amount.
Design Document Viewing Period: September 10, Reiwa 8 to September 28, Reiwa 8.
Design Document Viewing Location: Ichikikushino City Website
Application Deadline for Bidding Participation: Friday, September 18, Reiwa 8, 5:00 PM.
Application Location for Bidding Participation: Kagoshima Prefecture Municipalities Electronic Bidding System.
Documents to be submitted for bidding participation: List of assigned engineers (Construction) 1 copy (form available on website).
Bid Recipient (Application form, bid form, power of attorney, contract): Ichikikushino City Waterworks, Kenji Nakaya, Mayor of Ichikikushino City.
Notification of Bidding Participation Confirmation Submission Deadline: Thursday, September 24, Reiwa 8, 5:00 PM.
On-site Briefing Session Date/Time: None
Question Submission Deadline: Friday, September 18, Reiwa 8, 5:00 PM.
Question Submission Location: Waterworks and Sewerage Division, Finance Division, Contract Management Section.
Question Response Deadline: Thursday, September 24, Reiwa 8, 5:00 PM. (Responses will be provided as needed, but this is the final deadline.)
Question Response Location: Depending on the content of the question, Ichikikushino City Website.
Bid Submission Period: Friday, September 25, Reiwa 8, 8:30 AM to Monday, September 28, Reiwa 8, 4:00 PM.
Bid Opening Date/Time: Tuesday, September 29, Reiwa 8, 9:25 AM.
Bid Opening Location: Ichikikushino City Hall, Kushikino Government Building, 2nd Floor, Finance Division.
Invalid Bids:
1. If the breakdown of construction costs is not submitted.
2. If the breakdown of construction costs is deemed not submitted.
(a) If a part of the breakdown of construction costs is not submitted (including blank submissions).
(b) If the document is unrelated to the breakdown of construction costs.
(c) If it is the breakdown of construction costs for another project.
(d) If the breakdown of construction costs is missing a seal (excluding submissions via electronic bidding).
(e) If the specifications or other instructions are not met.
Qualification Requirements:
1. Not falling under the provisions of Article 167-4 of the Local Autonomy Law (Cabinet Order No. 16 of 1947).
2. Must have a permit under Article 3, Paragraph 1 of the Construction Industry Act (Law No. 100 of 1949) and be registered in the Ichikikushino City Construction Work Bidding Qualification Register.
3. Not be in a period of business suspension under Article 28, Paragraph 3 of the Construction Industry Act.
4. Must meet the conditions presented by the city at the time of the announcement.
5. Must be able to properly assign a site supervisor under Article 19-2 of the Construction Industry Act and a chief or supervising engineer under Article 26 of the same law for the work.
6. Must not be under a suspension of bidding during the period from the announcement to the bid, in accordance with the provisions of the Ichikikushino City Qualified Contractor Suspension Guidelines (Ichikikushino City Public Notice No. 26 of Reiwa 18).
7. If the bidder has a tax obligation to Ichikikushino City, there must be no arrears in city taxes, etc.
8. Must not have been subject to a transaction suspension order by an electronic exchange or a suspension of transactions from a major business partner.
9. Must not be a party for whom a rehabilitation procedure decision has been made or a rehabilitation procedure has been initiated under the Corporate Rehabilitation Law, or a party for whom a reconstruction procedure decision has been made or a reconstruction procedure has been initiated under the Civil Reconstruction Law.
10. Must not be in violation of other laws, regulations, or rules related to the construction industry.
Invalid Bids:
1. Bids submitted by persons who are not qualified to participate in the bidding.
2. Bids found to be collusive or otherwise fraudulent.
3. Cases where a breakdown of construction costs is requested and falls under the following:
4. Bids that violate other matters previously instructed by the Mayor.
Notes (*):
1. When submitting the bidding application form and bid form, use the Kagoshima Prefecture Municipalities Electronic Bidding System.
2. If a breakdown of construction costs is requested, attach the breakdown of construction costs (for bid attachment) (form available on the website).
3. If electronic bidding is not possible, submit a paper bid application form by 5:00 PM the day before the bid submission deadline and obtain approval.
4. When submitting a paper bid, submit it in person to the Finance Division, Contract Management Section at least 30 minutes before the bid opening date/time.
5. Site supervisors, chief engineers, and supervising engineers must not have been employed within 3 months of the bid application date.
6. For bid award, the bid price will be the amount written on the bid form plus 10% of that amount (rounded down to the nearest yen if there are fractions less than one yen). Therefore, bidders must write the amount equivalent to 110% of their estimated contract amount on the bid form, regardless of whether they are subject to or exempt from consumption tax and local consumption tax.
7. Other matters are in accordance with the Ichikikushino City Electronic Bidding Operation Rules.
Location Map Reiwa 8 Fiscal Year Water Single No. 10 Municipal Road Gonoara-Gatashita Line Water Distribution Pipe Relocation Work (Section 2) ( ) Kushikino Gymnasium Kushikino High School Ishikawa Mountain Community Center Terushima East Park Municipal Road Shimohirano Moto Line Municipal Road Gonoara-Gatashita Line Municipal Road Gonoara-Gatashita Line Location Map Reiwa 8 Fiscal Year Water Single No. 10 Municipal Road Gonoara-Gatashita Line Water Distribution Pipe Relocation Work (Section 2) Municipal Road Beppu-Shimohira Line 1267.4 Terushima East Park Municipal Road Ikurasakoh Line City Hall Kushikino Government Building Kagoshima Main Line National Route 3
Existing Water Distribution Pipe New Water Distribution Pipe Mizuho Town Hirano Plan View S=1:500 [Municipal Road Gonoara-Gatashita Line] Reiwa 8 Construction Water Distribution Pipe 2. Kaki φ201. Maezono et al. 1 unit φ25HNo,1No,2Municipal Road Shioya-Mikura Town LineMunicipal Road Gonoara-Gatashita LineEarthwork Section ⑤ (HPPEφ50)Shirasu Backfill Work (Good quality soil)Main Restoration Temporary RestorationUpper road base work (Graded crushed stone)Lower road base work (Cut crushed stone)S=1:20 As Pavement H=800ShirasuExisting sewer pipeExisting NTT pipeMunicipal Road Showa Dori/Midori-cho 2nd LineMunicipal Road Shimohirano Moto LineOverhead side ditch 300x300Connection part ①B.P [Municipal Road Gonoara-Gatashita Line]E.P (NO,2+22.2) [Municipal Road Gonoara-Gatashita Line]New valve φ150New fire hydrant φ75New valve φ150New valve φ150New valve φ150New valve φ50Municipal Road Showa Dori/Midori-cho 2nd Line963863150 35030Buried marker sheet Single/Aluminum W=150100 Temporary pavement work (Recycled coarse aggregate asphalt) Surface layer work (Recycled dense aggregate asphalt)600100 40701008021049080010063923963Construction DrawingsExisting VP φ40 H=UnknownExisting VP φ50Existing VP φ50Existing VP φ150 H=1000Existing HiRRVP φ50 H=600Existing HiRRVP φ50 H=600Existing DIP φ200 H=1200Existing DIP φ100 H=1200(Assumed)Existing HiRRVP φ50 H=800Existing HiRRVP φ50 H=600HExisting HiVP φ40 H=600(Constructed in Reiwa 5)HExisting HiVP φ40 H=600(Constructed in Reiwa 1)Existing DIP φ150 H=1200(Assumed)Existing DIP φ150 H=1200(Assumed)Existing HiVP φ40 H=600HExisting VP φ50 H=Unknown(Completed in Reiwa 6_Section 1)Existing DIP φ200 H=1200Existing HPPEφ200 H=800(Completed in Reiwa 6_Section 1)Existing VP φ40 H=UnknownExisting HPPEφ200 H=800( ) Kushikino Gymnasium Kushikino High School Ishikawa Mountain Community Center Terushima East Park Municipal Road Shimohirano Moto Line Municipal Road Gonoara-Gatashita LineEarthwork Section ① (HPPEφ200)ShirasuShirasu Backfill Work (Good quality soil)Main Restoration Temporary RestorationUpper road base work (Graded crushed stone)Lower road base work (Cut crushed stone)S=1:20 As Pavement H=800Earthwork Section ② (HPPEφ150)ShirasuShirasu Backfill Work (Good quality soil)Main Restoration Temporary RestorationUpper road base work (Graded crushed stone)Lower road base work (Cut crushed stone)S=1:20 As Pavement H=800Earthwork Section ③ (HPPEφ100)ShirasuShirasu Backfill Work (Good quality soil)Main Restoration Temporary RestorationUpper road base work (Graded crushed stone)Lower road base work (Cut crushed stone)S=1:20 As Pavement H=800Earthwork Section ④ (HPPEφ50)ShirasuShirasu Backfill Work (Good quality soil)Main Restoration Temporary RestorationUpper road base work (Graded crushed stone)Lower road base work (Cut crushed stone)S=1:20 As Pavement H=800Earthwork Section ⑤ (HPPEφ50)ShirasuShirasu Backfill Work (Good quality soil)Main Restoration Temporary RestorationUpper road base work (Graded crushed stone)Lower road base work (Cut crushed stone)S=1:20 As Pavement H=800Earthwork Section ⑥ (HPPEφ75)ShirasuShirasu Backfill Work (Good quality soil)Main Restoration Temporary RestorationRoad base work (Cut crushed stone)S=1:20 As Pavement (Sidewalk) H=800Existing continuous valve φ150 (for cast iron pipe)NTT buried pipe H=1.66mNTT buried pipe H=1.35mNTT buried pipe H=1.26mMunicipal Road Gonoara-Gatashita Line30Buried marker sheet Single/Aluminum W=150100 Temporary pavement work (Recycled coarse aggregate asphalt) Surface layer work (Recycled dense aggregate asphalt)60050 150 100 10050100170350800Base layer work (Recycled coarse aggregate asphalt)1050115030Buried marker sheet Single/Aluminum W=150100 Temporary pavement work (Recycled coarse aggregate asphalt) Surface layer work (Recycled dense aggregate asphalt)60050 150 100 10050100170350800Base layer work (Recycled coarse aggregate asphalt)180980108030Buried marker sheet Single/Aluminum W=150100 Temporary pavement work (Recycled coarse aggregate asphalt) Surface layer work (Recycled dense aggregate asphalt)600100 1009040100110560300800950990Reiwa 8 Fiscal Year Water Single No. 10 Municipal Road Gonoara-Gatashita Line Water Distribution Pipe Relocation Work (Section 2) Reiwa Year Month Day Work Location Drawing Type Scale Drawing Number Creation Date Work Name Kagoshima Prefecture Ichikikushino City Ichikikushino City, Ebisu Town, etc. Figure Indication Plan View All 4 Leaves No. 1.
* Pavement thickness shall be restored to its original state.
Water distribution pipe laying work HPPEφ200 L=61.5m, HPPEφ150 L=63.1m [Municipal Road Gonoara-Gatashita Line] Construction length L=140.8m Valve installation work φ150x4 units, φ50x1 unit, Fire hydrant installation work φ75x1 unit, Water supply connections 2 units.
Water distribution pipe laying work HPPEφ200 L=61.5m, HPPEφ150 L=63.1m, HPPEφ100 L=1.4m [Municipal Road Gonoara-Gatashita Line] Construction length L=140.8m Valve installation work φ150x4 units, φ50x1 unit, Fire hydrant installation work φ75x1 unit, Water supply connections 2 units.
(H=600)L=60.7mEarthwork Section ②Earthwork Section ④ (H=800)(H=800)L=61.5mEarthwork Section ① (H=800)L=2.8mEarthwork Section ② (H=800)L=2.2mEarthwork Section ⑥ (H=800)L=3.1mEarthwork Section ② (H=800)L=1.4mEarthwork Section ③L=2.5mEarthwork Section ⑤ (H=800)L=7.4mHPPEφ75 L=2.2m, HPPEφ50 L=8.0m, HiVPφ150 L=3.5m,