July 28 Announcement (Civil Engineering General BC) Announcement of Graded General Competitive Bidding. Project Name: Takenoura Mikosawa Aburaya Line Slope Countermeasures Construction
TSURUOKA CITY PUBLIC NOTICE NO. 126
ANNOUNCEMENT OF GRADED GENERAL COMPETITIVE BIDDING
We hereby announce that a graded general competitive bidding will be conducted as follows, in accordance with the provisions of Article 167-6 of the Local Autonomy Act Enforcement Order (Cabinet Order No. 16 of 1947) and Article 15 of the Tsuruoka City Contract Regulations (Tsuruoka City Regulation No. 54 of 2005).
July 28, Reiwa 8
Satoshi Sato, Mayor of Tsuruoka City
1. Place and Date of Bidding and Bid Opening
(1) Place: Large Conference Room, 6th Floor, Tsuruoka City Hall
(2) Date and Time: Thursday, August 20, Reiwa 8, 9:40 AM
2. Matters for Competitive Bidding
(1) Project Name: Takenoura Mikosawa Aburaya Line Slope Countermeasures Construction
(2) Project Location: Within Nishi-me, Tsuruoka City
(3) Project Details: As per the design documents (On-site explanation meeting will not be held).
If there are any doubts regarding the design documents, they will be accepted in writing.
① Question Acceptance Date: Wednesday, August 5, Reiwa 8, by 10:00 AM
② Answer: Friday, August 7, Reiwa 8, from 4:00 PM
(4) Construction Period: August 27, Reiwa 8 to November 13, Reiwa 8
(5) Estimated Price: ¥5,070,000 (excluding consumption tax and local consumption tax).
For the determination of the successful bid, the bid price will be the amount written in the bid form plus an amount equivalent to 10/100 of that amount (if there is a fraction of less than 1 yen, it will be rounded down). Therefore, bidders shall write in the bid form an amount equivalent to 100/110 of the estimated contract desired amount, regardless of whether they are taxable or tax-exempt businesses for consumption tax and local consumption tax.
3. Qualifications of Bidders
(1) The bidder must be graded in accordance with the "Tsuruoka City Construction Work Designated Competitive Bidding Participant Grading Regulations" (Tsuruoka City Public Notice No. 19 of 2005) and meet all of the following requirements:
① Work Type: Civil engineering (general)
② Grade: B, C
③ Requirement for Head Office/Branch Office within the City: Must have its head office within the city.
④ Engineer Requirement: --------------------------------------------------
⑤ Construction Experience: --------------------------------------------------
⑥ Other: --------------------------------------------------
(2) The bidder must not fall under Article 49, Item 11 of the Tsuruoka City Construction Work Contract General Conditions regarding the exclusion of violent groups.
(3) For public works subject to the Construction Industry Act, a supervising engineer or chief engineer must be appointed to manage the technical aspects of construction work on the construction site. Therefore, please confirm the planned personnel in advance. Also, please refer to the "Supervising Engineer System Operation Manual" on the Ministry of Land, Infrastructure, Transport and Tourism website for proper operation of the supervising engineer system. * Regarding "V. Maintenance of Construction System Ledger and Creation of Construction System Diagram" in the "Supervising Engineer System Operation Manual," please refer to the "Tsuruoka City Guidelines for Proper Management of Prime Contractor and Subcontractor Relationships in Construction Work." (https://www.city.tsuruoka.lg.jp/sangyo/nyusatsu/nyuusatukeiyakuseido/syakaihokenmikanyu.html)
(4) Regarding the site supervisor, please refer to "(Notice) Requirements for Concurrent Site Supervisor Positions in Construction Work" posted on the city's website under "Bidding Information." The site supervisor for this project may concurrently serve as the site supervisor for another project only with the approval of the contracting authority based on the successful bidder's application, when the placement of a supervising engineer (including a special supervising engineer) is not required.
4. Location for Inspection of Contract Provisions, etc.
(1) Viewing Location: Tsuruoka City website and Contract Management Division, 3rd Floor, Tsuruoka City Hall.
(2) Viewing Period: Until the day before the bidding date.
* Drawings, etc., can be borrowed by contacting us in advance by phone or other means. Please note that in some cases, all data may be posted on the Tsuruoka City website as electronic data.
5. Bid Bond and Contract Deposit
(1) Bid Bond: Exempt.
(2) Contract Deposit: An amount equivalent to 1/10 of the contract amount.
6. Bidder Application and Confirmation
(1) Submit 2 copies of the "Application for Confirmation of Graded General Competitive Bidding Participation Qualifications" to the Contract Management Division, 3rd Floor, Tsuruoka City Hall, or the Regional Development Promotion Division, Regional Government Office, by Tuesday, August 18, Reiwa 8 (mail is acceptable, enclose a return envelope; must arrive by the deadline). One copy will be returned with a reception stamp.
(2) To be a prime contractor for public works subject to the Construction Industry Act, a valid "Evaluation Results Notice of Business Scale, etc. / Comprehensive Evaluation Score Notice" (hereinafter referred to as "Results Notice") is required. You cannot undertake public works simply by applying for a business performance review; you must have completed the review and received the results notice to apply for bidding and participate in bidding. At the time of application acceptance, we will confirm the Results Notice valid until after the contract conclusion date. Please copy it to the back of the application form when applying. Attaching it as a separate document is also possible.
* The bidder must not be subject to a suspension of bidding on any day during the period from the final day of application acceptance to the contract conclusion. If suspended after application acceptance, the application will be canceled, and participation in bidding will not be allowed. If suspended between the successful bid decision and contract conclusion, the successful bid decision will be canceled.
7. Other
(1) Bidding Conditions: Please refer to the "Bidding Conditions," "Tsuruoka City Bidding Guidelines," and "Tsuruoka City Graded General Competitive Bidding Implementation Guidelines for Construction Work." Bidding may be canceled in accordance with Article 10 of the "Tsuruoka City Graded General Competitive Bidding Implementation Guidelines for Construction Work."
(2) When bidding, submit a construction cost breakdown of the same amount as the first bid amount, with the location, company name, and representative's name filled in and sealed (unit prices are not required for the cost breakdown items). Failure to submit will result in disqualification from bidding.
(3) This project is subject to the Tsuruoka City Variable Minimum Reserve Price System. For the determination of the successful bidder, the bidder who submits the lowest bid at or above the minimum reserve price within the range of the estimated price will be selected. Bids below the minimum reserve price will result in disqualification. For details, please refer to the "Tsuruoka City Variable Minimum Reserve Price System Implementation Guidelines" on the city's website. (https://www.city.tsuruoka.lg.jp/sangyo/nyusatsu/nyuusatukeiyakuseido/301227henndougata.html)
(4) For contracts exceeding ¥1.3 million, an advance payment can be requested. For contracts of ¥10 million or more that meet the requirements, an interim advance payment can be requested. (Article 36, Paragraphs 1 and 3 of the Tsuruoka City Construction Work Contract General Conditions)
8. Contact Information: Contract Management Division, General Affairs Department, Tsuruoka City Hall. Phone (Direct Dial): 35-1154
Reiwa 8
Takenoura Mikosawa Aburaya Line Slope Countermeasures Construction Design Document
Tsuruoka City
Cost Breakdown for this Project
Location Category: General
Impact on Traffic: Yes
(2) Construction Category / Work Type / Classification / Detail Specification Unit Quantity Unit Price Amount Remarks
Road Improvement Work
Earthwork
Excavation
Transport of soil, etc.
Site to Kakuganji, 10.4 km
m3 30
No. 1 Unit Price Table
Slope Work
Slope shaping
Cut slope, no site constraints
m2 280
No. 2 Unit Price Table
Slope protection work
Vegetation base spraying work, thickness 4 cm
m2 280
No. 3 Unit Price Table
Temporary Work
Removal of temporary materials
Loading/transport of site-generated materials
Site to Aburaya, L=2.0 km
t 10
No. 4 Unit Price Table
Traffic Management Work
Traffic guide guard
B person 12
No. 5 Unit Price Table
Direct Construction Cost Total
Common Temporary Work Total
Common Temporary Work
Site Environment Improvement Cost
Net Construction Cost
Site Management Cost
Total Construction Cost
General Management Cost (including contract guarantee fee)
Amount requiring monetary guarantee from the contractor
Consumption Tax Equivalent Amount
Total Amount
-
1 -
Tsuruoka City
Construction Department
Civil Engineering Division
Civil Engineering Work Special Specifications
Takenoura Mikosawa Aburaya Line Slope Countermeasures Construction
1. Application of Common Specifications
For the execution of this project, the "Common Specifications for Civil Engineering Work (Common Specifications for Civil Engineering Work, Civil Engineering Work Construction Management Standards and Specifications, Reference Materials) established by the Yamagata Prefectural Government Prefectural Development Department, April Reiwa 8" must be followed. The priority of the specifications shall be in the order of "Special Specifications," "Common Special Specifications," and "Common Specifications." Revisions made after April Reiwa 8 can be found on the following website, and the latest version shall apply.
* Revisions to the Common Specifications can be confirmed on the following page.
(http://www.pref.yamagata.jp) → Prefectural Information → Introduction to Yamagata Prefecture → Organization Guide → Department of Civil Engineering → Construction Planning Division → Common Specifications (Civil Engineering Work)
2. Special Provisions for Common Specifications
The special provisions for the common specifications are as follows:
Volume 1 Common Volume
Chapter 1 General Provisions
1-1. Margin Period System
1-2. Handling of Relaxation of Supervising Engineer's Exclusive Duty
1. In this project, when a supervising engineer to whom the provisions of Article 26, Paragraph 3, Proviso of the Construction Industry Act applies (hereinafter referred to as "Special Supervising Engineer") is to be assigned, the "Handling of Supervising Engineers and Assistants in Tsuruoka City Ordered Works" shall apply.
2. When a special supervising engineer or a supervising engineer's assistant is assigned, or when the need for assignment ceases, CORINS shall be registered appropriately.
1-3. Work Type
The work type shall be general civil engineering work (road improvement work).
- 2 -
1-4. Subcontracting
If any part of the work is subcontracted, regardless of the subcontract amount, a subcontract plan (change) report, a list of subcontractors, and a copy of the subcontract agreement for the relevant work must be submitted. A construction system ledger and diagram must also be prepared and submitted promptly to the supervisor. If subcontracted work is performed without submitting a subcontract plan (change) report, the work may be temporarily suspended.
1-5. Period of Engineer's Exclusivity
1. The period from the conclusion of the contract to the commencement of on-site construction (period until the establishment of the site office, delivery of materials, or commencement of temporary work) does not require the exclusive presence of the chief engineer or supervising engineer on the construction site. The date of commencement of on-site construction shall be determined in consultation with the supervisor after the successful bid decision.
2. The period after the completion of construction, inspection, and only administrative procedures and clean-up remain does not require the exclusive presence of the chief engineer or supervising engineer on the construction site. The date of completion of inspection shall be the date when the contracting authority notifies the contractor of the confirmation of project completion.
1-6. Pavement Engineer Assignment
1-7. Steel Bridge Painting Technician Assignment
1-8. Standard Cross-Section Ordering
For projects ordered with a standard cross-section, the current situation shall be surveyed, and construction drawings such as the longitudinal plan of the ditch (water channel) and the pavement area layout shall be created and approved in consultation with the supervisor. If construction commences before obtaining the supervisor's approval, the work may be temporarily suspended or modified. Please note that approval may take about one week due to the contracting authority's review. When planning, consider road surface drainage, and be sure to investigate the gradient of ditches upstream and downstream, as well as drainage channels for inflow and outflow.
1-9. Design Change Procedures
Design changes shall be handled in accordance with the construction contract general conditions and the common specifications for civil engineering work. The basic concept and procedures shall be in accordance with Chapter 1 "Design Change Guidelines" and Chapter 3 "Work Suspension Guidelines" of the "Collection of Materials for Smooth Construction of Civil Engineering Work (Revised February Reiwa 7)" by the Yamagata Prefectural Civil Engineering Work Smooth Construction Promotion Council.
1-10. Lifting Equipment
Lifting equipment shall be a crane truck or a backhoe with a crane function as standard. If other equipment must be used, the supervisor's written approval must be obtained.
1-11. Notification to Adjacent Residents
Before commencing construction, prepare a "Construction Notice" with an attached map showing the construction area, and distribute it to the local neighborhood association chairman and adjacent residents after obtaining the supervisor's approval. When performing work that requires complete road closure, install advance warning signs and provide notification to relevant organizations (kindergartens, nurseries, day services, etc.).
- 3 -
1-12. Public-Private Boundary
In principle, boundary inspections shall be conducted before commencing construction. When installing ditches, they shall be installed at the public-private boundary. If it is not possible to install them at the boundary, ditches shall be installed with the supervisor's approval and the consent of the landowner or residents, and the public-private boundary shall be clearly marked with boundary stakes, etc. After installing boundary stakes, etc., submit a record to the supervisor.
1-13. Obstructing Items for Construction
1. Underground buried items, etc.
(1) During the current situation survey, confirm the surrounding conditions (overhead power lines, NTT lines, etc.). For buried items, confirm using the "Application for Certificate of Underground Buried Items and Certificate."
(2) If necessary, conduct trial excavations to investigate the type, location, etc., of underground buried items and report the clearance from underground buried items, etc., to the supervisor with drawings and photographs.
(3) If underground buried items, etc., pose an obstacle as a result of (2), the supervisor shall request relocation from the facility manager of the underground buried items, etc., and commence this project after the facility manager completes the relocation work for the obstructing items.
2. If items that obstruct construction (public sewage manholes, water meters, etc.) are identified, consult with the supervisor promptly regarding the design documents.
1-14. Site-Generated Materials (Reusable Site Materials)
Regarding secondary products generated from the removal of existing facilities, consult with the supervisor regarding the disposal method and quantity confirmation. Record and submit the consultation details in the construction meeting minutes.
1-15. Construction By-products
1. Specified construction waste (concrete, asphalt, construction debris) generated by this project shall be transported to a recycling facility.
2. In accordance with Article 6 of the Construction Recycling Act, "Fair Burden of Costs for Recycling of Construction Waste," the disposal facilities for specified construction waste specified in the conditions are as follows. After completion of transport, the industrial waste management ticket (manifest) must be presented to the supervisor upon request.
3. If the contractor chooses a method other than the specified conditions in the preceding paragraph for their own convenience, they shall explain it during the pre-contract explanation as stipulated in Article 1, Chapter 1, Section 1-1-12, "Construction By-products," Paragraph 2 of the Common Special Specifications for Civil Engineering Work.