Public Notice of Bidding
Work subject to the two-day weekend trial (contractor-designated type)
November 10, Reiwa 8
In accordance with the provisions of Article 234, Paragraph 1 of the Local Autonomy Act, we hereby announce the following regarding the conclusion of a contract for construction work through general competitive bidding, pursuant to Article 167-6, Paragraph 1 of the Local Autonomy Act Enforcement Order and Article 4 of the Hiroshima City Contract Regulations.
Kazumi Matsui, Mayor of Hiroshima City
Construction Name: Municipal Housing Bath Boiler, etc. Installation (8-1) Construction
Construction Location: Suzugaminecho, Nishi Ward, and others
Construction Outline: Installation of bath boilers and bathtubs in municipal housing.
(1) Suzugamine Nishi Apartments: 2 units
(2) Tosaka Higashi Jyo Apartments: 6 units
(3) Tosaka Hyakuta Apartments: 4 units
(4) Kabe Nakajima Apartments: 5 units
* Details are as per the design drawings and specifications (hereinafter referred to as "Design Documents, etc.").
Construction Period: 100 days from the date of contract conclusion.
Estimated Price: To be announced after award decision.
Minimum Limit Price: To be announced after award decision.
Bid Classification:
* This construction work is subject to electronic bidding using the Hiroshima City Electronic Bidding System.
* Paper bids are not permitted for this construction work; only electronic bidding via the system is allowed.
* Bidding procedures shall be in accordance with the "Hiroshima City Electronic Bidding System Usage Agreement" and "Hiroshima City Electronic Bidding Operation Standards".
* This construction work is subject to electronic lottery.
Bid Participation Conditions:
Bidders must satisfy all of the following conditions.
Qualifications:
* Must not be subject to the provisions of Article 167-4 of the Local Autonomy Act Enforcement Order and Article 2 of the Hiroshima City Contract Regulations.
* Must be certified as a participant in Hiroshima City construction competitive bidding for fiscal years Reiwa 7 and 8.
* Must have obtained an IC card in the bidder's name and completed user registration for the electronic bidding system.
* Other qualification requirements are as per the tender explanation document.
Certified Construction Type: Pipework
Grade Classification, etc.: Must be certified as "D" or "C".
Business Office Location, etc.: Must have a head office within Hiroshima City.
* "Head office" refers to the principal place of business under the Construction Industry Act.
Company Construction Experience: Must have experience in the following construction work, completed and delivered as the prime contractor on or after April 1, Reiwa 11:
* Pipework construction with a contract amount (excluding consumption tax, etc.) of 50% or more of the city's design amount for this construction (excluding consumption tax, etc.).
* However, construction experience as a member of a joint venture is limited to those with an investment ratio of 20% or more.
* Limited to experience in the certified construction types listed above.
Annual Average Completed Construction Value:
Annual average completed construction value for pipework must be the highest or second highest compared to other construction types.
* "Other construction" annual average completed construction value will also be treated as one construction type.
* Annual average completed construction value is based on the "Management Scale Evaluation Result Notification/Overall Evaluation Score Notification" with the examination standard date within 1 year and 7 months prior to the submission date of the general competitive bidding participation qualification confirmation application for this construction.
Technical Staff:
① Must be able to assign a chief technical officer or supervising engineer for pipework construction to the work.
If the contract amount is 45 million yen (including tax) or more, they must be assigned exclusively.
Furthermore, if a supervising engineer (meaning a supervising engineer as defined in Article 26, Paragraph 3, Item 2 of the Construction Industry Act, hereinafter the same) is assigned concurrently under Special Exception 2, a supervising engineer assistant (meaning a person who assists the duties stipulated in Article 26, Paragraph 4, Item 1 of the same Act, to be performed by the concurrently assigned supervising engineer) must be assigned exclusively to the work.
However, technical staff must comply with the provisions of Article 26, Paragraphs 1 to 5 of the same Act.
② Technical staff must be directly and constantly employed by the bidder on the bid opening date, and have been employed for 3 months or more prior to the bid opening date.
However, if the contract amount is less than 45 million yen (including tax), the technical staff must be directly and constantly employed by the bidder on the bid opening date and have been employed from the day before the bid opening date.
③ The concurrent assignment of technical staff is permitted within the scope of the conditions specified in the tender explanation document, even if exclusive assignment is required.
Other:
* Constructors who have a capital or personnel relationship with the design consultant (Aiko & Co. Architects) for this construction work cannot participate.
* Those who do not meet the bid participation conditions cannot participate.
* Furthermore, those who cannot be selected in accordance with the provisions of Article 28, Item 2, Item 3 (a) to (o), and Item 5 (a) of the Hiroshima City Construction Competitive Bidding Handling Guidelines cannot participate.
* Those who cannot confirm fulfillment of the obligation to join and pay social insurance (health insurance and employees' pension insurance) and labor insurance (employment insurance) cannot participate (excluding those who are not subject to the obligation to join each insurance).
For details, please check the Hiroshima City website (https://www.city.hiroshima.lg.jp/) under "Information for Businesses" -> "Bidding and Contract Information" -> "Overview of Bidding and Contract Systems" -> "Construction and Construction Consulting Services" -> "Construction" -> "System and Confirmation Documents for Social Insurance and Labor Insurance Enrollment".
Distribution of Tender Explanation Documents, etc.
Submission of Bid Forms, etc.
[Distribution of Tender Explanation Documents]
Download from the Hiroshima City website (https://www.city.hiroshima.lg.jp/) under "Information for Businesses" -> "Bidding and Contract Information" -> "Electronic Bidding" -> "Hiroshima City Electronic Procurement System Portal Site" -> "2. Procurement Information Public System" -> "1. General Public Use" -> "Direct Search Bidding/Quotation Information". Search for this construction work and download from "Details".
[Bid Form Acceptance Period]
Using the electronic bidding system, from 8:30 AM to 5:00 PM on November 25 (Wed) and 26 (Thu), Reiwa 8 (until 4:00 PM on the final day).
If unable to submit via the electronic bidding system due to unavoidable reasons, submit the bid form and attached documents in person by 4:00 PM on the final day after submitting the prescribed notification.
[Attached Document Acceptance Period]
Same as the bid form acceptance period.
(However, for those participating in bidding using the electronic bidding system, if the file size of the attached documents exceeds the capacity specified in Article 11, Paragraph 2 of the Hiroshima City Electronic Bidding Operation Standards, submit them in person by 4:00 PM on the final day of the bid form acceptance period.)
[Bid Form and Attached Document Submission Location]
Contract Section (details below)
Viewing and Distribution of Design Documents, etc.
[Viewing Period]
From the date of public notice to November 26, Reiwa 8 (Thursday), from 8:30 AM to 5:00 PM (until 4:00 PM on the final day) (excluding Hiroshima City holidays (holidays as defined in Article 1, Paragraph 1 of the Hiroshima City Holidays Ordinance (1991, Hiroshima City Ordinance No. 49), hereinafter the same)).
[Viewing and Distribution of Design Documents, etc.]
Download from the Hiroshima City website (https://www.city.hiroshima.lg.jp/) under "Information for Businesses" -> "Bidding and Contract Information" -> "Electronic Bidding" -> "Hiroshima City Electronic Procurement System Portal Site" -> "2. Procurement Information Public System" -> "2. User Functions" -> "6. Entrance to Hiroshima City Procurement Information Public System (User Functions)" -> "To the Login Screen" -> "Hiroshima City Procurement Information Public System (User Functions)". Log in using your contractor number (5 digits) and password, then download from "Bidding/Quotation Information".
Note: The design drawings for this construction work are attached after being reduced from original size A2 to A3.
* When viewing or downloading design documents, etc., you will need to enter the download password specified in the "Download Confirmation Form".
* When downloading design documents, etc., the "Download Confirmation Form" attached to the procurement information public system must be submitted with the qualification confirmation application after the bid opening.
* The "Download Confirmation Form" is only issued during the viewing period mentioned above, so please keep it safe.
* Viewing is also available at the construction project management section below.
Inquiries regarding Design Documents, etc.
[Inquiry Submission Period]
From the date of public notice to November 16, Reiwa 8 (Monday) (excluding Hiroshima City holidays).
[Response Document Viewing and Distribution Period via System]
From November 19, Reiwa 8 (Thursday) to November 26, Reiwa 8 (Thursday), from 8:30 AM to 5:00 PM (until 4:00 PM on the final day) (excluding Hiroshima City holidays).
[Viewing and Distribution of Design Documents and Responses]
Download from the Hiroshima City website (https://www.city.hiroshima.lg.jp/) under "Information for Businesses" -> "Bidding and Contract Information" -> "Electronic Bidding" -> "Hiroshima City Electronic Procurement System Portal Site" -> "2. Procurement Information Public System" -> "2. User Functions" -> "6. Entrance to Hiroshima City Procurement Information Public System (User Functions)" -> "To the Login Screen" -> "Hiroshima City Procurement Information Public System (User Functions)". Log in using your contractor number (5 digits) and password, then download from "Bidding/Quotation Information".
* Viewing is also available at the construction project management section below.
Bid Opening Date, etc.
[Bid Opening Date and Time]
November 27, Reiwa 8 (Friday), 9:30 AM
[Bid Opening Location]
Hiroshima City Hall, Main Building, 15th Floor, Bidding Room
[Number of Bids]
If no bid is submitted within the range of the estimated price and above the minimum limit price, a re-bid will be conducted once by sending a re-bid notice via the electronic bidding system.
Submission of Bid Participation Qualification Confirmation Application, etc.
[Submission of Application, etc.]
To be submitted by the lowest bidder after the bid opening (as described in Section 7 of the tender explanation document).
[Submission Location]
Construction Project Management Section (details below)
Notification of Bid Participation Qualification Confirmation Results and Bid Results:
After confirmation of bid participation qualifications, the successful bidder will be notified via the electronic bidding system.
Bid Cancellation:
Bidding may be canceled if the fairness of the bidding is deemed to have been compromised due to the actions of a bidder or an error in the発注者's bidding procedure.
Invalid Bids:
Bids submitted by persons who do not meet the bid participation conditions stated in this public notice, who have made false statements in their applications, who have violated the bidding conditions, or whose submitted bid participation qualification confirmation applications are incomplete (including incorrect entries) and cannot be verified, shall be deemed invalid.
Other:
* This bid is a post-bid qualification confirmation type general competitive bid, where eligibility is confirmed after the bid opening.
* For the determination of the successful bidder, the contract amount will be the amount entered by the successful bidder in the electronic bidding system or stated in the bid form, plus 10% of that amount (if there is a fraction of less than 1 yen, that fraction will be rounded down). Therefore, bidders must enter or state an amount equivalent to 110/100 of their estimated contract amount, regardless of whether they are taxable or exempt business operators for consumption tax and local consumption tax.
* This construction work is a trial project for securing two days off per week ("contractor-designated type").
If 4 days off per week (8 days off per month) are not achieved, the contract price will be subject to negotiation for reduction based on the situation, in accordance with Article 24 of the Hiroshima City Construction Contract Terms and Conditions.
For details, please refer to the Hiroshima City website (https://www.city.hiroshima.lg.jp/) under "Information for Businesses" -> "Urban Development" -> "Information Technology and Technical Management of Public Works" -> "To Construction Contractors" -> "Hiroshima City Trial Implementation of Two Days Off Per Week Construction".
* Other conditions are as per the tender explanation document and "To Those Participating in Competitive Bidding for Construction Projects".
Bid Bond: Exempted
Contract Deposit: Required (10% or more of the contract amount)
Contract Section:
1-6-34 Kokutaiji-cho, Naka Ward, Hiroshima City
Finance Bureau, Contract Department, Construction Contract Section (15th Floor, Main Building)
(Phone) 082-504-2280
(Email) keiyaku-koji@city.hiroshima.lg.jp
(FAX) 082-504-2612
Construction Section:
1-6-34 Kokutaiji-cho, Naka Ward, Hiroshima City
Urban Development Bureau, Building Department, Equipment Section (7th Floor, Main Building)
(Phone) 082-504-2306
(Email) setsubi@city.hiroshima.lg.jp
(FAX) 082-504-2181
Appendix
September 1, Reiwa 8
Finance Bureau, Contract Department, Construction Contract Section, Hiroshima City
Regarding the Trial Implementation of "Labor Cost Dumping Survey"
The national government has created and published the "Guidelines for Public Purchasers to Prevent Labor Cost Dumping," which summarizes the submission of bid amount breakdowns and points to note regarding the specific implementation of "Labor Cost Dumping Surveys."
While the national guidelines stipulate confirmation of the breakdown of costs in writing ("Reason Statement") when the direct construction cost falls below a certain level, this city will, in principle, request a Reason Statement along with the application documents from all bidders who are requested to submit application documents, regardless of whether the direct construction cost falls below a certain level.
This Reason Statement is not for stating the reason why the cost fell below a certain level, but rather to explain the calculation method and thinking behind the bid amount and construction cost breakdown, and to confirm the appropriateness of labor costs based on the submitted Reason Statement.
Even if a reasonable response cannot be confirmed, the contract will be concluded, but the purchaser will report to the "Construction G-men" (investigators under Article 40-4 of the Construction Industry Act).
However, this trial implementation is limited to general competitive bids (excluding unit price contracts) for which the Finance Bureau, Contract Department, Construction Contract Section concludes the contract.
Target of "Labor Cost Dumping Survey"
This trial will be conducted only for general competitive bids (excluding unit price contracts) for which the Finance Bureau, Contract Department, Construction Contract Section concludes the contract.
Designated competitive bids and discretionary contracts are not subject to this.
Submission of "Reason Statement"
After the bid opening, all bidders requested to submit application documents must submit a Reason Statement along with the application documents to the construction project management section listed in the bid notice (the deadline for submitting the Reason Statement is the same as for the application documents).
For general competitive bids (WTO-covered), submit the Reason Statement to the construction project management section listed in the bid notice by the prescribed deadline based on the suspension notice.
Implementation Period:
Starting with public notices issued on or after September 1, Reiwa 8.
If a "Reason Statement" is not submitted for public notices issued on or after November 1, Reiwa 8, the bid of the successful candidate will be invalidated.
Reason Statement
Year Month Day
Mayor of Hiroshima City
Location: X City, X Ward, X Town, X-chome, X-ban, X-go
Trade Name or Company Name: XXXX Co., Ltd.
Representative Director: XXXX XXXX
Regarding the construction of
, the reason for bidding at the said labor cost is as follows.