Default lot
This tender has been awarded
Awarded to INGINERIE DRUMURI SI PODURI S.R.L.; PROCONS GROUP; FREYROM; INTEGRATED ROAD SOLUTIONS SRL — €57,187,269
About This Opportunity
TranslatedThis tender concerns the provision of expropriation and design services, along with the execution of works for the "Connection Passage between DN1C and Tetarom III Industrial Park" investment objective. The contracting authority reserves the right to modify the contract in accordance with Article 221 of Law 98/2016, provided these modifications do not constitute a substantial change as defined in Article 221, paragraph 7. Price revision clauses are included as per Article 221, paragraph 1, letter a) of Law 98/2016, anticipating potential contract adjustments. These include price adjustments based on the formula specified in Article 31 of Government Emergency Ordinance 64/2022 for projects financed by non-reimbursable external funds. Furthermore, the contract allows for contractor replacement under specific conditions outlined in Article 221, paragraph 1, letter d), points i) and ii) of Law 98/2016, ensuring no substantial modification occurs. Specifically, if the contractor faces implementation difficulties or is unable to fulfill contractual obligations due to their own fault, a nominated third-party supporter, previously identified in the bid and contract, will assume the contractual obligations. This transfer will not alter the scope, responsibilities, or general nature of the initial contract. The tender details the conditions under which a new contractor can be appointed, ensuring continuity and adherence to the project's objectives while maintaining the integrity of the procurement process.
This is a works contract in the construction and civil works, architecture and engineering and transport and logistics sectors, with a focus on Roads, Construction Supervision, Architectural Design and Feasibility Studies. Located in Romania, Europe, this opportunity is open to firms and consortiums.
Published through TED - Tenders Electronic Daily (EU), a national government procurement portal. Public procurement tenders follow the country's national bidding regulations and may have specific eligibility and documentation requirements for civil works in the construction and civil works sector. Works contracts of this nature generally require demonstrated experience in similar infrastructure projects, adequate equipment and technical personnel, and financial capacity including bank guarantees. This contract has already been awarded. The information is published for transparency and market intelligence purposes.
Description
Auto-translated from roThe subject of the contract consists in the provision of expropriation and design services, as well as the Execution of works for the realization of the investment objective: Connection passage between DN1C and Tetarom III Industrial Park. The Contracting Authority reserves the right to modify the contract according to art. 221 of Law 98/2016, provided that these modifications do not fall within the provisions of art. 221 para. 7 of Law 98/2016, i.e., they do not represent a substantial modification. Revision clauses according to art. 221 para. (1) letter a) of Law 98/2016, which anticipate possible changes during the contract execution are: • Price adjustments according to cl. 48 of this Contractual Agreement by applying the price adjustment formula mentioned in art. 31 of OUG 64/2022 regarding the adjustment of prices and the value of general estimates in projects financed by non-reimbursable external funds (art. 221 para. (1) letter a). • Replacement of the Contractor: 1) When the Contractor is replaced by a new Contractor, under the conditions provided by art. 221 para. (1) letter d) item i) of Law 98/2016, only in cases where the respective replacement does not involve substantial modifications of the contract: In case the Contractor encounters implementation difficulties (the contract is not properly executed by the contractor or there are delays in the execution activities for reasons solely attributable to the Contractor, regardless of whether it is the fault of an economic operator within the association or the fault of the association as a whole) or is unable to execute the contract, the third-party supporter introduced in the offer and nominated in the contract will take over the fulfillment of the contractual obligations according to the firm commitment, annex to the contract, without reducing, extending or eliminating the obligations and responsibilities stipulated in the initial contract and without affecting its general character; 2) When the Contractor is replaced by a new Contractor under the conditions provided by art. 221 para. (1) letter d) item ii) of Law 98/2016, in the situation where the rights and obligations of the initial Contractor resulting from the public procurement contract are taken over, as a result of a universal or universal succession in a reorganization process, including through merger, division, acquisition or insolvency, by another economic operator that meets the qualification and selection criteria initially established, provided that this modification does not involve other substantial modifications; 3) When the Contractor is replaced by a new Contractor, under the conditions provided by art. 221 para. (1) letter d) item iii) of Law 98/2016, in the event that the Beneficiary/Contracting Authority assumes the Contractor's obligations towards its subcontractors, respectively they towards the Beneficiary/Contracting Authority. In this situation, in case of early termination of the contract, at the request of the Beneficiary/Contracting Authority, the Contractor will assign its contracts concluded with its subcontractors to the contracting authority upon its request. • Other modifications: 1) Change of the company's name and/or legal form, changes that do not result in the creation of a new legal entity; 2) replacement of the association leader by one of the members of the association taking over this role and/or modification of the initial composition of the association by another associate/ the remaining associates taking over the attributions of one/more members, provided that after the modification of the composition, the members of the association meet the qualification and selection requirements initially established in the award documentation and respecting, where applicable, the conditions provided in art. 186 of Law 98/2006; 3) modifications generated by the change of key/non-key personnel, which will be carried out according to the corresponding clause in the General Contractual Conditions; 4) modification of the partners' percentages of the contract value, to the extent that such a modification ensures the continued fulfillment of the qualification requirements from the award documentation, does not affect the application of the qualitative evaluation factors within the criteria...
Data provenance
This notice is sourced from TED - Tenders Electronic Daily (EU) and was originally published on March 13, 2025. Last refreshed 10 days ago. Original language: ro. BidsFactory mirrors official procurement notices and links back to the source for full legal text.
Frequently asked questions about this tender
How can I submit a bid?
Visit TED - Tenders Electronic Daily (EU) to access the full notice, required documents, and submission instructions provided by the contracting authority.
Is this tender still open?
No — the contract has already been awarded to INGINERIE DRUMURI SI PODURI S.R.L.; PROCONS GROUP; FREYROM; INTEGRATED ROAD SOLUTIONS SRL. The award notice is archived on BidsFactory for transparency and market intelligence.
Who is the contracting authority?
This notice was issued by COMPANIA NATIONALA DE ADMINISTRARE A INFRASTRUCTURII RUTIERE S.A. prin D.R.D.P. CLUJ in Romania. The authority is responsible for evaluating bids, awarding the contract, and managing performance.
What type of contract is this?
This is a Works contract in the Construction & Civil Works sector. The classification helps bidders match the opportunity to their qualifications and registered scope of supply.
How much was the contract awarded for?
INGINERIE DRUMURI SI PODURI S.R.L.; PROCONS GROUP; FREYROM; INTEGRATED ROAD SOLUTIONS SRL was awarded the contract for €57,187,269. The figure reflects the value disclosed by the contracting authority in the award notice.
Where will the contract be performed?
The contract is for delivery in Romania. Foreign bidders should review local registration, taxation, and any in-country presence requirements before submitting.
Find tenders like this automatically
Set up alerts and filters that match your business — never miss a relevant opportunity again.
Sectors & Categories
Contracting Authority
Companies That Won Similar