Lot 1: Maintenance of roads, paths, and surface drainage;
Lot 2: Maintenance of sidewalks and adjacent areas;
Lot 3: Maintenance of road markings
- approx. 230 m² natural stone paving to be removed
- approx. 175 m² concrete and clinker paving to be removed
- approx. 20 m² paving to be removed, laid in concrete
- approx. 100 m natural stone curb to be removed
- approx. 100 m concrete curb to be removed
- approx. 50 m drainage channel to be removed
- approx. 725 m bituminous pavement to be separated
- approx. 530 m² non-hazardous waste to be removed and disposed of (milling)
- approx. 80 t non-hazardous waste to be removed and disposed of (bound)
- approx. 300 m² non-hazardous waste to be removed and disposed of (breaking up)
- approx. 225 m² concrete slab to be broken up
- approx. 175 m² Bkl 3-6 to be removed according to profile
- approx. 200 t non-hazardous waste to be removed and disposed of (unbound surface course)
- approx. 3,600 m² formation to be produced
- approx. 14,000 m verges to be planed
- approx. 14,000 m verges to be milled
- approx. 50 m infiltration ditch to be produced
- approx. 50 m drainage infiltration line to be produced
- approx. 100 m road ditch to be profiled
- approx. 100 m road ditch to be produced
- approx. 100 m road gully to be produced
- approx. 6,000 m ditch to be cleared
- approx. 100 m natural curbs to be regulated
- approx. 120 m natural curbs of the client to be supplied and set
- approx. 650 m concrete curbs to be supplied and set (raised and rounded curbs)
- approx. 150 m concrete curbs to be supplied and set (dropped curbs)
- approx. 30 m Kassel special curb to be supplied and set, basic type
- approx. 350 m² drainage channel made of channel stones to be produced
- approx. 350 m² drainage channel made of paving stones of the client to be produced
- approx. 750 t frost protection layer 0/32 to be produced
- approx. 750 t frost protection layer 0/45 to be produced
- approx. 125 t ballast base course 0/45 to be produced
- approx. 500 m² hydraulically bound base course to be produced, 0/45 15 cm
- approx. 1,000 m² geotextile GRK 3
- approx. 1,200 m² dense asphalt concrete (DoB), grain size 0/11, 3 cm
- approx. 200 m² concrete paving (various shapes) to be produced
- approx. 1,235 m² asphalt base course to be produced
- approx. 600 m² asphalt binder course to be produced
- approx. 1,400 m² asphalt wearing course to be produced
- approx. 1,000 m² mastic asphalt to be produced
- approx. 520 m² asphalt base course to be produced
- approx. 3,000 m joint to be produced
- approx. 250 m² asphalt reinforcement grid to be supplied and laid
- approx. 30 pcs tree planting system to be produced
- approx. 20 pcs concrete angle elements to be supplied and set
- approx. 150 m repair of steel guardrail systems
- approx. 650 m² paved road including drainage channel to be removed and restored on HGT
- approx. 400 m² service road including drainage to be produced
- approx. 500 m² grass mowing
- approx. 250 m² natural stone paving to be removed
- approx. 150 m² concrete paver to be removed
- approx. 500 m² slab paving to be removed
- approx. 550 m² concrete slab to be broken up
- approx. 300 m² non-hazardous waste to be removed and disposed of (demolition)
- approx. 315 m concrete curbs to be removed
- approx. 15 m³ topsoil to be removed and stored
- approx. 10 m³ topsoil to be removed and disposed of
- approx. 6 m³ topsoil to be supplied and covered
- approx. 100 t non-hazardous waste to be removed and disposed of, unbound surface course, Z1
- approx. 80 m³ layers of base and surface courses to be removed, loaded, and disposed of
- approx. 20 m ditch profile to be restored
- approx. 50 m² ballast base course 0/45 to be produced
- approx. 135 m³ frost protection 0/32 to be produced
- approx. 780 m² asphalt base course to be produced
- approx. 15 t asphalt base course to be produced, profile leveling
- approx. 200 m natural curbs of the client to be set
- approx. 50 m natural curbs to be regulated
- approx. 620 m concrete curbs to be supplied and set, earthworks
- approx. 250 m system edge restraints to be supplied and set, PVC
- approx. 420 m concrete dropped curbs to be supplied and set, earthworks
- approx. 150 m² paving strip made of client's stones to be produced, 1-3 rows
- approx. 100 m² small paver channel to be produced, 3-5 rows
- approx. 30 m Kassel special curb to be supplied and set, basic type
- approx. 90 m² natural stone paving to be supplied and produced, mosaic paving
- approx. 30 m² natural stone paving to be supplied and produced, small paving
- approx. 500 m² gray concrete rectangular paving to be produced (with chamfer)
- approx. 500 m² gray concrete rectangular paving to be produced (without chamfer)
- approx. 310 m² concrete paving to be produced, 18x15.3x8 earth brown
- approx. 40 m² grooved slabs to be supplied and installed
- approx. 20 m² shed slabs to be supplied and installed
- approx. 20 m² studded slabs to be supplied and installed
- approx. 50 m² DoB 0/8 to be produced
- approx. 50 m² DoB 0/16 to be produced
- approx. 200 m² surface treatment DoB, 0/5
- approx. 15 t asphalt binder course to be produced
- approx. 300 m² asphalt wearing course to be produced
- approx. 100 m² asphalt wearing course made of PA 11 to be produced
- approx. 300 m² bitumen-containing binder to be sprayed
- approx. 50 m joint to be produced, 10 mm
- approx. 2 pcs concrete parts for road gully, long, without SF
- approx. 2 pcs concrete parts for road gully, short, without SF
- approx. 2 pcs cover D 400, 300x500
- approx. 2 pcs cover D 400, 500x500
- approx. 10 m box culvert to be produced
- approx. 40 m³ soil of class 3-6 to be removed and disposed of
- approx. 10 pcs foundation for lighting mast to be supplied and set
- approx. 5 pcs block step 100 cm
- approx. 5 pcs block step 150 cm
- approx. 10 pcs tree planting system to be produced
- approx. 6 m steel tube railing
- approx. 30 m infill bar railing
- approx. 500 m² road marking to be removed
- approx. 15,000 m narrow lines to be produced
- approx. 2,000 m bicycle protection lane to be produced
- approx. 200 m wide lines to be produced
- approx. 40 pcs turning arrows to be produced
- approx. 40 pcs straight-ahead arrows to be produced
- approx. 50 pcs bicycle pictograms to be produced
- approx. 100 m crossings to be produced